FAST-41 Missed Date:Section 106 Review: Consultation initiated with SHPO/THPO (Agency Action)
Agency Milestone Date of 03/06/2025 for Consultation initiated with SHPO/THPO (Agency Action) has passed by 1 business days
Agency Milestone Date of 03/06/2025 for Consultation initiated with SHPO/THPO (Agency Action) has passed by 1 business days
Agency Milestone Date of 03/06/2025 for ESA Consultation Request Package Submitted (Agency Action) has passed by 1 business days
Agency Milestone Date of 03/06/2025 for Consultation initiated with SHPO/THPO (Agency Action) has passed by 1 business days
Triggered missed date from extending ESA Consultation Request Package Submitted (Agency Action) within 30 days of its current target date which was 02/06/2025 and extended to 03/06/2025
Triggered missed date from extending ESA Consultation Request Package Submitted (Agency Action) within 30 days of its current target date which was 02/06/2025 and extended to 03/06/2025
Agency Milestone Date of 01/31/2025 for Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) has passed by 1 business days
Agency Milestone Date of 01/30/2025 for Consultation initiated with SHPO/THPO (Agency Action) has passed by 1 business days
Agency Milestone Date of 01/10/2025 for Publication of Public Notice (Agency Action) has passed by 1 business days
EDD completed 1/2/25 - typo date entered wrong as 3/30/26. It should be 4/6/26. Corrected 1/8/25 to April date.