Milestone Extension: Section 10 Rivers and Harbors Act of 1899 and Section 404 Clean Water Act
The Section 10/404 final completion date is dependent upon the final completion date of BOEM’s NEPA action. For this project, the USACE review will require 120 days between issuance of the ROD and issuance of USACE’s Section 10/404 decision. Therefore, an extension of the Section 10/404 final completion date is requested based upon the extension of the ROD milestone.