NRC submitted an EDD request on March 31 to the Permitting Council. The Executive Director granted a Nuclear Regulatory Commission (NRC) request to extend the final completion dates for the Section 106 consultation and the Bureau of Land Management's EA and Mine Plan of Operations on April 14, 2026.
Cooperating under NEPA
Milestones:
PROJECT WEBSITE: https://deweyburdock.info/
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/26/2026
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Mining
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Nuclear Regulatory Commission
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Interior, Bureau of Land Management
Description:
The Dewey Burdock In-Situ Recovery (ISR) Uranium Project is a proposed uranium production facility located in Fall River and Custer Counties, South Dakota. The project will recover uranium from subsurface sandstone ore bodies through ISR technology, which involves the injection of a lixiviant solution into production wellfields to dissolve uranium minerals in place and pump the uranium-bearing solution to a central processing plant for recovery. The use of ISR technology allows for minimal surface disturbance compared to conventional open-pit or underground uranium mining. The project consists of wellfield areas, a central processing plant, supporting infrastructure and environmental protection systems. The project has been licensed by the NRC (Source Material License SUA-1600) and is progressing toward final state and federal authorizations required to begin commercial production.
The Executive Director granted a Nuclear Regulatory Commission (NRC) request to extend the final completion dates for the Section 106 consultation and the Bureau of Land Management's EA and Mine Plan of Operations on April 14, 2026. The Executive Director determination is posted here.
Original Target Date: 05/15/2026
Milestone: Issuance of decision for Mine Plan of Operations (Agency Action)
Requested extensions greater than 30 days for this Action are shown below:
Financial assurance received (Applicant Action) extended by 46
From: 05/15/2026
To: 06/30/2026