Agency Milestone Date of 05/13/2026 for FWS determines ESA Consultation Package is Complete - Informal (Agency Action) has passed by 1 business days
Milestones:
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
05/03/2027
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Mining
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Army, US Army Corps of Engineers - Regulatory
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Interior, Fish and Wildlife Service
Description:
The Hell’s Kitchen Critical Minerals & Power Project will convert geothermal brine into steam to generate electrical energy. The power plant will use the geothermal brine to produce electrical power from its steam and the direct lithium extraction plant will convert the dissolved lithium into battery-grade lithium hydroxide and/or lithium carbonate for the battery industry. The Project is located southeast of the Salton Sea, Calipatria, California.
The Executive Director granted a U.S. Army Corps of Engineers request to extend completion dates for all actions on October 10, 2025. The Executive Director Determination is posted here.