USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Approved

Milestone Extension: Endangered Species Act Consultation (NOAA-NMFS)

BOEM conducted a comprehensive status of the development of the EIS and found that publication of the Draft EIS on September 19, 2025, is no longer feasible. BOEM estimated that publication of the Draft EIS would be delayed by approximately 10 months (308 day shift) to July 24, 2026. Therefore, NMFS subsequently adjusted the remaining milestones for NMFS actions accordingly.

Milestone Extension: Right-of-Way Authorization (DOI-BLM)

Because the Commission’s milestone target dates, including those for issuance of the draft and final NEPA documents and order, were modified to account for the additional time needed for the project sponsor to file required information, dependent milestone target dates are being modified accordingly.  The Commission’s request for an Executive Director determination includes additional information.    

Milestone Extension: Lease of Power Privilege (DOI-BOR)

  Because the Commission’s milestone target dates, including those for issuance of the draft and final NEPA documents and order, were modified to account for the additional time needed for the project sponsor to file required information, dependent milestone target dates are being modified accordingly.  The Commission’s request for an Executive Director determination includes additional information.

Milestone Extension: Endangered Species Act Consultation (DOI-FWS)

Because the Commission’s milestone target dates, including those for issuance of the draft and final NEPA documents and order, were modified to account for the additional time needed for the project sponsor to file required information, dependent milestone target dates are being modified accordingly.  The Commission’s request for an Executive Director determination includes additional information.    

Milestone Extension: Section 404 Clean Water Act

Because the Commission’s milestone target dates, including those for issuance of the draft and final NEPA documents and order, were modified to account for the additional time needed for the project sponsor to file required information, dependent milestone target dates are being modified accordingly.  The Commission’s request for an Executive Director determination includes additional information.