Milestone Extension: Endangered Species Act Consultation (NOAA-NMFS)
BOEM NEPA schedule was extended 119 days, so NMFS milestones adjusted accordingly.
BOEM NEPA schedule was extended 119 days, so NMFS milestones adjusted accordingly.
Section 106 consultation concluded milestone is dependent on the NEPA timeline and affected commensurately by delays.
COP final decision/agency action milestone is dependent on the NEPA timeline and affected commensurately by delays.
Vineyard Northeast’s delayed submission of a complete Terrestrial Archaeological Resources Assessment (TARA) has resulted in delays to the development of the draft EIS.
BOEM is requesting these completion date modifications due to the timing of the Project Sponsor’s submission of a revised Construction and Operations Plan (COP) containing additional data and assessments that BOEM requires prior to issuing a Notice of Intent (NOI) to prepare an Environmental Impact Statement (EIS) under NEPA.
BOEM is requesting these completion date modifications due to the timing of the Project Sponsor’s submission of a revised Construction and Operations Plan (COP) containing additional data and assessments that BOEM requires prior to issuing a Notice of Intent (NOI) to prepare an Environmental Impact Statement (EIS) under NEPA.
BOEM is requesting these completion date modifications due to the timing of the Project Sponsor’s submission of a revised Construction and Operations Plan (COP) containing additional data and assessments that BOEM requires prior to issuing a Notice of Intent (NOI) to prepare an Environmental Impact Statement (EIS) under NEPA.
BOEM is requesting these completion date modifications due to the timing of the Project Sponsor’s submission of a revised Construction and Operations Plan (COP) containing additional data and assessments that BOEM requires prior to issuing a Notice of Intent (NOI) to prepare an Environmental Impact Statement (EIS) under NEPA.
BOEM is requesting these completion date modifications due to the timing of the Project Sponsor’s submission of a revised Construction and Operations Plan (COP) containing additional data and assessments that BOEM requires prior to issuing a Notice of Intent (NOI) to prepare an Environmental Impact Statement (EIS) under NEPA.
BOEM is requesting these completion date modifications due to the timing of the Project Sponsor’s submission of a revised Construction and Operations Plan (COP) containing additional data and assessments that BOEM requires prior to issuing a Notice of Intent (NOI) to prepare an Environmental Impact Statement (EIS) under NEPA.