USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Approved

Milestone Extension: Right-of-Way Authorization (DOI-BLM)

Because the Commission’s milestone target dates, including those for issuance of the draft and final NEPA documents and order, were modified to account for the additional time needed for the project sponsor to file required information, dependent milestone target dates are being modified accordingly.  The Commission’s request for an Executive Director determination includes additional information.    

Milestone Extension: Lease of Power Privilege (DOI-BOR)

  Because the Commission’s milestone target dates, including those for issuance of the draft and final NEPA documents and order, were modified to account for the additional time needed for the project sponsor to file required information, dependent milestone target dates are being modified accordingly.  The Commission’s request for an Executive Director determination includes additional information.

Milestone Extension: Endangered Species Act Consultation (DOI-FWS)

Because the Commission’s milestone target dates, including those for issuance of the draft and final NEPA documents and order, were modified to account for the additional time needed for the project sponsor to file required information, dependent milestone target dates are being modified accordingly.  The Commission’s request for an Executive Director determination includes additional information.    

Milestone Extension: Section 404 Clean Water Act

Because the Commission’s milestone target dates, including those for issuance of the draft and final NEPA documents and order, were modified to account for the additional time needed for the project sponsor to file required information, dependent milestone target dates are being modified accordingly.  The Commission’s request for an Executive Director determination includes additional information.    

Milestone Extension: Endangered Species Act Consultation (DOI-FWS)

BLM’s justification for this permitting timetable extension is based on the timing of the Project Sponsor’s submission of a cultural resource survey and Bald and Golden Eagle survey, which BLM requires prior to proceeding with the NEPA process for the Project. To account for the additional time needed for the Project Sponsor to complete these surveys and BLM to subsequently review the Project Sponsor’s submissions, BLM is requesting an extension of approximately six months for issuance of the final NEPA document and the right-of-way authorization.

Milestone Extension: Right-of-Way Authorization (DOI-BLM)

BLM’s justification for this permitting timetable extension is based on the timing of the Project Sponsor’s submission of a cultural resource survey and Bald and Golden Eagle survey, which BLM requires prior to proceeding with the NEPA process for the Project. To account for the additional time needed for the Project Sponsor to complete these surveys and BLM to subsequently review the Project Sponsor’s submissions, BLM is requesting an extension of approximately six months for issuance of the final NEPA document and the right-of-way authorization.