The project sponsor submitted an updated Construction and Operations Plan (COP) to BOEM on September 29, 2025. On October 1, 2025 the government shut down through November 12, 2025, impacting BOEM’s ability to review the COP submission. In addition, multiple comments were not addressed by the project sponsor in their September 29, 2025 COP submission and the project sponsor indicated that the Underwater Acoustic Assessment, Historic Resources Visual Effects Assessment, and Seascape and Landscape Visual Impact Assessment and associated COP updates would be submitted later in time.