USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Milestone Extension: Environmental Assessment (EA)

Submitted by georgeann.smal… on

The explanation for the milestone date change was outlined in the Executive Director Determination request submitted to the Permitting Council on March 30, 2026.

Action
Project Name: Responsible Agency:
Bureau of Land Management
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
In Progress
POC Name:
Christopher Rye
POC Title:
Geologist
POC Email:

Milestones:

Determination to prepare an Environmental Assessment (EA) (Agency Action)
Completed Date:
Issuance of a Final EA (Agency Action)
Current Target Date:
EA Process Concluded (Agency Action)
Milestone Under Executive Director Review:
This milestone currently has an extension request pending
Current Target Date:
Milestone
EA Process Concluded (Agency Action)
Milestone Under Executive Director Review:
This milestone currently has an extension request pending
Current Target Date:
Project

PROJECT WEBSITE: https://deweyburdock.info/

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
05/29/2026

1 out of 6

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Mining

SECTOR
Mining

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Nuclear Regulatory Commission

LEAD AGENCY
Nuclear Regulatory Commission

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Bureau of Land Management

Description:

The Dewey Burdock In-Situ Recovery (ISR) Uranium Project is a proposed uranium production facility located in Fall River and Custer Counties, South Dakota. The project will recover uranium from subsurface sandstone ore bodies through ISR technology, which involves the injection of a lixiviant solution into production wellfields to dissolve uranium minerals in place and pump the uranium-bearing solution to a central processing plant for recovery. The use of ISR technology allows for minimal surface disturbance compared to conventional open-pit or underground uranium mining. The project consists of wellfield areas, a central processing plant, supporting infrastructure and environmental protection systems. The project has been licensed by the NRC (Source Material License SUA-1600) and is progressing toward final state and federal authorizations required to begin commercial production.

field_status
System Comments
Furthest out
Original Target Date: 04/15/2026
Milestone: Issuance of a Final EA (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

EA Process Concluded (Agency Action) extended by 68
From: 05/15/2026
To: 06/22/2026
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
EA Process Concluded (Agency Action)
Milestone Under Executive Director Review:
This milestone currently has an extension request pending
Current Target Date:
Furthest Original Target Date Milestone
Issuance of a Final EA (Agency Action)
Current Target Date: