Approved

Milestone Extension: Section 408 Permit

The Section 408 milestones are dependent on BOEM’s EIS action milestones. A shift of BOEM’s EIS action milestones by 180 days results in a commensurate shift to the Section 408 action milestones. Therefore, an extension of the Section 408 milestones is requested based upon the extension of BOEM’s EIS milestones. The requested milestone changes are shown in the table below.

Milestone Extension: Section 10 Rivers and Harbors Act of 1899 and Section 404 Clean Water Act

The Section 10/404 milestones are dependent on BOEM’s EIS action milestones. A shift of BOEM’s EIS action milestones by 180 days results in a commensurate shift to the Section 10/404 action milestones. Therefore, an extension of the Section 10/404 milestones is requested based upon the extension of BOEM’s EIS milestones. The requested milestone changes are shown in the table below.

Milestone Extension: Endangered Species Act Consultation (DOI-FWS)

The ESA milestones "FWS Determines ESA Consultation Package is Complete - Formal" and "ESA Consultation Concludes" are dependent on BOEM’s EIS action milestones. A shift of BOEM’s EIS action milestones by 180 days results in a commensurate shift to these ESA action milestones. Therefore, an extension is requested based upon the extension of BOEM’s EIS milestones. The requested milestone changes are shown in the table below.

Milestone Extension: Magnuson-Stevens Fishery Conservation and Management Act, Section 305 Essential Fish Habitat (EFH) Consulta

The EFH milestones "NOAA Determines EFH Assessment is Complete" and “NOAA Issues any EFH Conservation Recommendations" are dependent on BOEM’s EIS action milestones. A shift of BOEM’s EIS action milestones by 180 days results in a commensurate shift to these EFH action milestones.  Therefore, an extension of the EFH milestones is requested based upon the extension of BOEM’s EIS milestones. The requested milestone changes are shown in the table below.

Milestone Extension: Endangered Species Act Consultation (NOAA-NMFS)

The ESA milestones "NOAA Determines ESA Consultation Package is Complete - Formal" and "ESA Consultation Concludes" are dependent on BOEM’s EIS action milestones. A shift of BOEM’s EIS action milestones by 180 days results in a commensurate shift to these ESA action milestones. Therefore, an extension is requested based upon the extension of BOEM’s EIS milestones. The requested milestone changes are shown in the table below.

Milestone Extension: Section 106 Review

The implementation of the above-mentioned policies is essential to ensure that development of the EIS is consistent with current legal and policy frameworks, and requires additional time for intra-agency coordination, stakeholder engagement, and technical analysis. These contributing factors have resulted in a 180-day delay to the development of the EIS. Therefore, the NEPA milestone dates have shifted 180-days as detailed in the table below.

Milestone Extension: Environmental Impact Statement (EIS)

The implementation of the above-mentioned policies is essential to ensure that development of the EIS is consistent with current legal and policy frameworks, and requires additional time for intra-agency coordination, stakeholder engagement, and technical analysis. These contributing factors have resulted in a 180-day delay to the development of the EIS. Therefore, the NEPA milestone dates have shifted 180-days as detailed in the table below.