Approved

Milestone Extension: Right-of-Way Authorization (DOI-BIA)

The Project Sponsor has asked for an additional five months to complete its coordination with the Pueblos and Tribes, which the Project Sponsor is engaged in as part of the Section 106 process. The Project Sponsor is continuing to work with the Pueblos and Tribes on cultural surveys and sensitivity concerns and is making small refinements to the alignment of the proposed route to avoid certain cultural resources. The Section 106 consultation and route alignment affect timing of the Environmental Assessment, which then affects the cooperating agency dependent actions.

Milestone Extension: Section 404 Clean Water Act

The Project Sponsor has asked for an additional five months to complete its coordination with the Pueblos and Tribes, which the Project Sponsor is engaged in as part of the Section 106 process. The Project Sponsor is continuing to work with the Pueblos and Tribes on cultural surveys and sensitivity concerns and is making small refinements to the alignment of the proposed route to avoid certain cultural resources.

Milestone Extension: Right-of-Way Authorization (DOI-FWS)

The Project Sponsor has asked for an additional five months to complete its coordination with the Pueblos and Tribes, which the Project Sponsor is engaged in as part of the Section 106 process. The Project Sponsor is continuing to work with the Pueblos and Tribes on cultural surveys and sensitivity concerns and is making small refinements to the alignment of the proposed route to avoid certain cultural resources.

Milestone Extension: NPS Permit

The Project Sponsor has asked for an additional five months to complete its coordination with the Pueblos and Tribes, which the Project Sponsor is engaged in as part of the Section 106 process. The Project Sponsor is continuing to work with the Pueblos and Tribes on cultural surveys and sensitivity concerns and is making small refinements to the alignment of the proposed route to avoid certain cultural resources.

Milestone Extension: Right-of-Way Authorization (DOI-BLM)

The Project Sponsor has asked for an additional five months to complete its coordination with the Pueblos and Tribes, which the Project Sponsor is engaged in as part of the Section 106 process. The Project Sponsor is continuing to work with the Pueblos and Tribes on cultural surveys and sensitivity concerns and is making small refinements to the alignment of the proposed route to avoid certain cultural resources.

Milestone Extension: Section 106 Review

NTIA is seeking to extend the Project’s permitting timetable at the request of the Project Sponsor. The Project Sponsor has asked for an additional five months to complete its coordination with the Pueblos and Tribes, which the Project Sponsor is engaged in as part of the Section 106 process

Milestone Extension: Environmental Assessment (EA)

NTIA is seeking to extend the Project’s permitting timetable at the request of the Project Sponsor. The Project Sponsor has asked for an additional five months to complete its coordination with the Pueblos and Tribes, which the Project Sponsor is engaged in as part of the Section 106 process

Milestone Extension: Section 408 Permit

A commensurate extension of the Section 10/404/408 final completion date is requested based upon the extension of the ROD milestone. Factors that inform the USACE final decision include the conclusion of Delaware Natural Resources and Environmental Control's (DNREC) Section 401 water quality certification (WQC) process.