FAST-41 Missed Date:Authorization and Certification: Issuance of decision for permit/approval (Agency Action

Submitted by Anonymous on

Agency Milestone Date of 04/02/2026 for Issuance of decision for permit/approval (Agency Action has passed by 1 business days

Action
Project Name: Responsible Agency:
US Army Corps of Engineers - Civil Works
Agency Status: Cooperating under FAST-41
Status:
Planned
POC Name:
Ryan White,
POC Title:
Chief (Acting) Real Estate Management and Disposal Branch

Description:

Applicant must submit a Consent to Cross Application to USACE in accordance with ER 405-1-12, Chapter 8, Paragraph 8-188.

Milestones:

Initial application received (Applicant Action)
Current Target Date:
Completed application received (Applicant Action)
Current Target Date:
Issuance of decision for permit/approval (Agency Action
Current Target Date:
Milestone
Issuance of decision for permit/approval (Agency Action
Current Target Date:
Project

PROJECT WEBSITE: Grain Belt Express

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/18/2027

1 out of 5

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Electricity Transmission

SECTOR
Electricity Transmission

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Army

LEAD AGENCY
Department of the Army, US Army Corps of Engineers - Regulatory

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of War Seal

Department of War, US Army Corps of Engineers - Regulatory

Department of the Army

Department of the Army, US Army Corps of Engineers - Section 408

Department of the Army

Department of the Army, US Army Corps of Engineers - Civil Works

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

Phase 1 of the Grain Belt Express (Project), a bi-directional high-voltage direct current (HVDC) transmission line spanning approximately 542 miles across Kansas and Missouri, will facilitate the delivery of domestically produced renewable energy generation to the Midcontinent Independent System Operator (MISO) and Associated Electric Cooperative Incorporated (AECI) territories in the Midwest. 

The Project consists of a 542-mile 600-kV HVDC overhead electric transmission line (HVDC Line), HVDC converter station sites, and AC transmission facilities that together will interconnect to existing power grids that are managed by Southwest Power Pool (SPP), MISO, and AECI.

Update (8/25/2025): In coordination with Grain Belt Express LLC, an applicant before the Department of Energy (DOE), Loan Programs Office (LPO), LPO requested a pause in all milestones and associated deadlines in the FAST-41 permitting timetable for Phase 1 of the Grain Belt Express Transmission Project (Project) for a period of 45 days, through October 8, 2025, subject to further extension. This pause of the permitting timetable for the Project was necessary because on July 23, 2025, the DOE terminated its conditional commitment for a loan guarantee for the Project. The requested pause was also necessary to provide Grain Belt Express LLC the time needed to establish permitting strategies related to the further advancement of the Project.

Update (10/01/2025): In coordination with Grain Belt Express LLC, an applicant before the Department of Energy (DOE), Loan Programs Office (LPO) requested a continuation of the pause in all milestones and associated deadlines in the FAST-41 permitting timetable for Phase 1 of the Grain Belt Express Transmission Project (Project) for a period of 45 days, through November 22, 2025, subject to further extension. This continuation of the pause of the permitting timetable for the Project was necessary because on July 23, 2025, the DOE terminated its conditional commitment for a loan guarantee for the Project, and to provide Grain Belt Express LLC the time needed to establish permitting strategies related to further advancement of the Project.

Update (11/14/2025): In coordination with Grain Belt Express LLC, an applicant before the Department of Energy (DOE), Loan Programs Office (LPO), LPO requested a continuation of the pause in all milestones and associated deadlines in the FAST-41 permitting timetable for Phase 1 of the Grain Belt Express Transmission Project (Project) for a period of 90 days, through February 20, 2026, subject to further extension. This continuation of the pause of the permitting timetable for the Project was necessary because on July 23, 2025, the DOE terminated its conditional commitment for a loan guarantee for the Project, and to provide Grain Belt Express LLC the time needed to establish permitting strategies related to further advancement of the Project.

Update (2/20/2026):  On January 22, 2026, the project sponsor requested this project move from paused to in-progress status for federal authorizations and reviews. The U.S. Army Corps of Engineers will serve as the lead federal agency for FAST-41. Posting of an updated timetable will occur on or before April 21, 2026.

 

 

field_status
System Comments
Agency Milestone Date of 04/02/2026 for Issuance of decision for permit/approval (Agency Action has passed by 1 business days
Approver Comments
The project was in paused status when this milestone was due on the original permitting timetable. USACE, as the new lead agency, is updating the overall project schedule to include this action.
Previous Action Status
New Action Status
Missed Date Process
No
Missed Date Triggered by Extension
No
New Milestone
Issuance of decision for permit/approval (Agency Action
Current Target Date:
Response Date