Milestone Extension: Environmental Impact Statement (EIS)
Project had been paused, waiting for revised POD from applicant. Schedule delays due to coordination with DRECP, CA CEQA requirements. And minor delay coordinating with another FAST-41 project, Desert Quartzite on location of their gen-tie line.