Milestone Extension: Section 106 Review
This milestone is dependent on the EIS which has an updated target completion date of 11/30/2018.
This milestone is dependent on the EIS which has an updated target completion date of 11/30/2018.
BSEE consulted with BOEM to change these dates, based on information from the project proponent. Hilcorp informed the Cooperating Agencies that it will not provide certain applications (such as this one) that are in its "Project Execution" phase, until it has made a business-case decision to sanction the project (by December 2018). BOEM (and the project sponsor), BSEE and the Project Proponent are all aware of this date change. BOEM is being reactive to the project proponent's request.
Project Sponsor indicated that a revised application will be submitted in June 2018, requiring the timeline to be adjusted accordingly. Additional information under the milestone (to be published).
Project sponsor indicated a revised application will be submitted in June. Timeline adjusted accordingly. See milestone description for additional information.
Agency staff tried to change the target date on December 27, 2017 (more than 30 days before the target date); however, due to staff leave over the Holidays, this update could not be made before the lock-out. Further, FPISC-OED failed to approve of the date change before the January 26, 2018 target date was missed. FPISC-OED has already approved via e-mail for this update to occur.
Project sponsor indicated that a revised application will be submitted in June, requiring the Corps to extend its timeline. Additional information found under the milestone (pending approval).
The schedule for this project has been updated to reflect the changes submitted to FPISC on January 12th, 2018. The DEIS has been delayed primarily due to additional analysis required for the Desert Renewable Energy Conservation Plan, and the California Public Utilities Commission review for CEQA adequacy. DOI has identified a new target completion date for the DEIS, and is expediting the remaining schedule accordingly.
From EPA: The date of issuance of the NPDES permit will need to be revised as a result of the overall schedule changes for the EIS. To be consistent with the new EIS timeline and expected issuance date of the EIS ROD, EPA would like the NPDES issuance date changed to November 13, 2018.
Delayed due to lapse in appropriations