USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Approved

Milestone Extension: Environmental Impact Statement (EIS)

Project sponsor had delays in providing BLM cultural information that is needed for the environmental analysis and 106 determinations of eligibility and findings of effect. BLM coordinated the updated schedule with Riverside County, USEPA, USFWS, and California Department of Fish and Wildlife. The BLM also consulted with the project sponsor in developing the updated schedule. The sponsor concurs with the schedule and are "encouraged and look forward to implementing the schedule [BLM] provided."

Milestone Extension: Section 106 Review

Project sponsor had delays in providing BLM cultural information that is needed for the environmental analysis and 106 determinations of eligibility and findings of effect. BLM coordinated the updated schedule with Riverside County, USEPA, USFWS, and California Department of Fish and Wildlife. The BLM also consulted with the project sponsor in developing the updated schedule. The sponsor concurs with the schedule and are "encouraged and look forward to implementing the schedule [BLM] provided."

Milestone Extension: Right-of-Way Authorization (DOI-BLM)

Project sponsor had delays in providing BLM cultural information that is needed for the environmental analysis and 106 determinations of eligibility and findings of effect. BLM coordinated the updated schedule with Riverside County, USEPA, USFWS, and California Department of Fish and Wildlife. The BLM also consulted with the project sponsor in developing the updated schedule. The sponsor concurs with the schedule and are "encouraged and look forward to implementing the schedule [BLM] provided."

Milestone Extension: Environmental Impact Statement (EIS)

Project had been paused, waiting for revised POD from applicant. Schedule delays due to coordination with DRECP, CA CEQA requirements. And minor delay coordinating with another FAST-41 project, Desert Quartzite on location of their gen-tie line.

Milestone Extension: Section 106 Review

Schedule back in progress, upon receipt of revised Plan of Development from proponent. Paused while waiting for revised POD, need for coordination with DRECP and California CEQA requirements. Additional minor delay occurred to coordinate with another FAST-41 project, solar Desert Quartzite, on that project's gen tie route.

Milestone Extension: Environmental Assessment (EA)

The applicant delayed sending the Site-Specific Plan of Development 6 (SPOD-6) until May 23, 2019. The project Sponsor (Proponent, Power Company of Wyoming) is make business decisions to ensure that their transmission line (Transwest Express) is on a similar construction timeline. Currently, the Chokecherry Sierra Madre Project is under construction on Phase I and the haul road and infrastructure for Phase II. The proponent has permitting in place to allow for construction for all of the 2019 construction season.