Milestone Extension: Right-of-Way Authorization (DOI-BLM)
BLM received approval to proceed with publishing the FEIS on September 18, 2019. Headquarters have reviewed and approved the extension.
BLM received approval to proceed with publishing the FEIS on September 18, 2019. Headquarters have reviewed and approved the extension.
BLM received approval to proceed with publishing the FEIS on September 18, 2019. Headquarters have reviewed and approved the extension.
The lead Federal agency has indicated that delays have occurred in NHPA compliance, and identified via email on September 26, 2019, that they recommend a revised target date of January 31, 2020, for the decision.
The Nevada SHPO is requiring more documentation and reports and they get an automatic 30 day extension on every request that they send to BLM.
The target date has now changed a week from the original date of 1/3 to 1/17 due to a partial lapse in government funding, earlier this year. Proponent is aware and tailored their submittal of applications to cooperating agencies with the 1/17 date in mind. All are aware of this change and are in support of this schedule.
Sponsor is not concerned with the date change, no other aspects of permitting timetable are affected. Justification for delay documented under the action in the dashboard. The DOI Cerpo is aware of the delay.
BLM received approval to proceed with publishing the FEIS on September 18, 2019. Headquarters have reviewed and approved the extension.
The new project date is 90 days after FERC’s new projected order date of 2/13/20. DOE's issuance of an export is dependent on the release of FERC's order.
Final Required Milestone Date of 05/10/2021 for Conclusion of ESA Consultation has passed by 5 business days
Execution of the 106 Programmatic Agreement was delayed pending proposed changes requested by one of the consulting parties. The project sponsor changed the date accordingly for the conclusion of the 106 PA and the Record of Decision which will not be issued on December 6, 2019. Issues were not included in the most recent quarterly CPP. The CERPO has been made aware. These delays will not have any significant impact on the project.