Milestone Extension: Outer Continental Shelf (OCS) Air Permit

Submitted by mary.boatman@b… on

The first public notice period of the draft OCS air permit ran from 6/24/2021 through 8/9/2021. EPA is planning a second notice period in October 2021 to solicit public feedback on a change in the draft OCS air permit requirements.

Action
Project Name: Responsible Agency:
Environmental Protection Agency
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
In Progress
POC Name:
Undine Kipka

Description:

EPA is responsible for issuing an Outer Continental Shelf (OCS) air permit under the Clean Air Act. EPA Region 1 will be the primary contact office and will coordinate with EPA Region 2 for this OCS air permit.

Milestones:

NOI to apply for an Air Permit submitted (Applicant Action)
Completed Date:
OCS Air Permit application submitted (Applicant Action)
Completed Date:
OCS Air Permit application complete (Applicant Action)
Completed Date:
Issuance of final decision/permit approval (Agency Action)
Current Target Date:
Milestone
Issuance of final decision/permit approval (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: South Fork Wind Farm - Deepwater Wind

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/18/2022

9 out of 9

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects
Major Infrastructure Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Environmental Protection Agency

Environmental Protection Agency

Description:

The purpose of the South Fork Wind Farm (the Project) is to generate electricity from an offshore wind farm and transmit it to the existing East Hampton Substation, part of the Long Island Power Authority (LIPA) electric transmission and distribution system in East Hampton, New York. The Project addresses the need identified by LIPA for new sources of power generation that can cost-effectively and reliably supply the South Fork of Suffolk County, Long Island, as an alternative to constructing new transmission facilities. The Project will also help LIPA achieve its renewable energy goals. The Project will enable Deepwater South Fork to fulfill its contractual commitments to LIPA pursuant to a Power Purchase Agreement (PPA) executed in 2017 resulting from LIPA's technology-neutral competitive bidding process.

The South Fork Wind Farm is located in federal waters on the Outer Continental Shelf (OCS), specifially in Bureau of Ocean Energy Management (BOEM) Renewable Energy Lease Area OCS-A 0517, approximately 19 miles southeast of Block Island, Rhode Island, and approximately 35 miles east of Montauk Point, New York; The South Fork Export Cable is located on the OCS, in New York State Territorial Waters, and in the Town of East Hampton, New York.

field_status
System Comments
Furthest out
Original Target Date: 10/31/2021
Milestone: Issuance of final decision for permit/approval

Requested extensions greater than 30 days for this Action are shown below:

Issuance of final decision for permit/approval extended by 79
From: 10/31/2021
To: 01/18/2022
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Issuance of final decision/permit approval (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
Issuance of final decision/permit approval (Agency Action)
Current Target Date: