Milestone Extension: Right-of-Way Authorization (DOI-BLM)

Submitted by william.dove@f… on

Corrected date to reflect previously completed milestone

Action
Project Name: Responsible Agency:
Bureau of Land Management
Status:
In Progress
POC Name:
Lane Cowger
POC Title:
Project Manager
POC Email:
Public Participation Website:

Description:

BLM is responding to an application for a right-of-way on public lands for (description of facility). If the BLM offers a right-of-way grant to the applicant, the target date for this action will be the offer date of the right-of-way grant to the applicant for their signature.

Milestones:

Initial application received (Agency Action)
Completed Date:
Completed application received (Agency Action)
Completed Date:
Final decision/agency action (Agency Action)
Completed Date:
Avian Protection Plan (Applicant Action)
Completed Date:
Milestone
Avian Protection Plan (Applicant Action)
Completed Date:
Project

PROJECT WEBSITE: Ten West Link Transmission Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/13/2022

5 out of 5

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Electricity Transmission

SECTOR
Electricity Transmission

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of Transportation

Department of Transportation, Federal Aviation Administration

Description:

DCR Transmission, LLC (DCRT) filed a right-of-way (ROW) application (SF-299) with the Bureau of Land Management (BLM) on September 14, 2014, that proposes to construct, operate, maintain, and decommission an electric transmission project in western Arizona and eastern California. The proposed Ten West Link 500 kilovolt (kV) Transmission Line Project (the Project) would consist of a 500kV transmission line traversing approximately 114 miles. The Project would increase transmission capacity by 3,200 megawatts (MW) and provide interconnection capability for new energy projects located near the Project.

The Project would begin at the Arizona Public Service Company (APS) Delaney Substation near Tonopah, Arizona, and terminate at the Southern California Edison (SCE) Colorado River Substation near Blythe, California. The Project would be located in Maricopa and La Paz counties in Arizona, and Riverside County in California.

field_status
System Comments
Furthest out
Original Target Date: 12/31/2018
Milestone: Notice to proceed

Requested extensions greater than 30 days for this Action are shown below:

Avian Protection Plan extended by 947
From: 02/21/2020
To: 08/04/2021
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Avian Protection Plan (Applicant Action)
Current Target Date: