Milestone Extension: Right-of-Way Authorization (DOD)
Project sponsor is aware of delay and is working with Navy to complete the NHPA Section 106 and Tribal Consultations by June 30. Date change does not affect the permitting timetable as it is not on the critical path. DoD CERPO has been informed and understands that project sponsor & the Navy have significant participatory roles in getting consultations completed.