USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

FAST-41 Missed Date: Outer Continental Shelf (OCS) Air Permit

Submitted by ajay.maheshwar… on

Triggered missed date from extending Issuance of final decision for permit/approval within 30 days of its current target date which was 10/31/2021 and extended to 01/18/2022

Action
Project Name: Responsible Agency:
Environmental Protection Agency
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
In Progress
POC Name:
Undine Kipka

Description:

EPA is responsible for issuing an Outer Continental Shelf (OCS) air permit under the Clean Air Act. EPA Region 1 will be the primary contact office and will coordinate with EPA Region 2 for this OCS air permit.

Milestones:

NOI to apply for an Air Permit submitted (Applicant Action)
Completed Date:
OCS Air Permit application submitted (Applicant Action)
Completed Date:
OCS Air Permit application complete (Applicant Action)
Completed Date:
Issuance of final decision/permit approval (Agency Action)
Current Target Date:
Milestone
Issuance of final decision/permit approval (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: South Fork Wind Farm - Deepwater Wind

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/18/2022

9 out of 9

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects
Major Infrastructure Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Environmental Protection Agency

Environmental Protection Agency

Description:

The purpose of the South Fork Wind Farm (the Project) is to generate electricity from an offshore wind farm and transmit it to the existing East Hampton Substation, part of the Long Island Power Authority (LIPA) electric transmission and distribution system in East Hampton, New York. The Project addresses the need identified by LIPA for new sources of power generation that can cost-effectively and reliably supply the South Fork of Suffolk County, Long Island, as an alternative to constructing new transmission facilities. The Project will also help LIPA achieve its renewable energy goals. The Project will enable Deepwater South Fork to fulfill its contractual commitments to LIPA pursuant to a Power Purchase Agreement (PPA) executed in 2017 resulting from LIPA's technology-neutral competitive bidding process.

The South Fork Wind Farm is located in federal waters on the Outer Continental Shelf (OCS), specifially in Bureau of Ocean Energy Management (BOEM) Renewable Energy Lease Area OCS-A 0517, approximately 19 miles southeast of Block Island, Rhode Island, and approximately 35 miles east of Montauk Point, New York; The South Fork Export Cable is located on the OCS, in New York State Territorial Waters, and in the Town of East Hampton, New York.

Update:

The Executive Director granted a BOEM request to extend the final completion date for “Outer Continental Shelf (OCS) Air Permit,” “Issuance of final decision for permit/approval” until 01/18/2022. The Executive Director determination will be posted when it becomes available.

field_status
System Comments
Triggered missed date from extending Issuance of final decision for permit/approval within 30 days of its current target date which was 10/31/2021 and extended to 01/18/2022
Approver Comments
Per John: Executive Director timely granted the extension request on this milestone but was delayed in updating the public facing dashboard.
Previous Action Status
New Action Status
Missed Date Process
No
Missed Date Triggered by Extension
Yes
New Milestone
Issuance of final decision/permit approval (Agency Action)
Current Target Date:
Response Date