Milestone Extension: Section 106 Review
NA
delay due to lapse in appropriations
Delayed due to lapse in appropriation
Due to the funding lapse at certain federal agencies between December 22, 2018, and January 25, 2019, an extension was necessary for cooperating agencies to complete their respective review. As such, the Commission issued a notice revising the schedule for issuance of the draft and final EISs and final order on February 28, 2019. Commission staff emailed the notice to the relevant agencies and project sponsor.
Due to the funding lapse at certain federal agencies between December 22, 2018, and January 25, 2019, an extension was necessary for cooperating agencies to complete their respective input. As such, the Commission issued a notice revising the schedule for issuance of the draft and final EISs and final order on February 28, 2019. Commission staff emailed the notice to the relevant agencies and project sponsor.
This date has been revised in accordance with OED email dated 2/27/2019.
Due to the funding lapse at certain federal agencies between December 22, 2018, and January 25, 2019, an extension was necessary for cooperating agencies to complete their respective review. As such, the Commission issued a notice revising the schedule for issuance of the draft and final EISs and final order on February 28, 2019. Commission staff emailed the notice to the relevant agencies and project sponsor.
The Commission’s previous notice of schedule, issued on August 31, 2018, identified issuance dates of November 8, 2019, for the final EIS, and February 6, 2020, for the final order (based on issuance of a draft EIS in February 2019). The previous notice stated that the forecasted schedule was based upon the project sponsor providing complete and timely responses to any data requests. In its partial data request responses filed in January and February 2019, the project sponsor states that it would provide the remainder of the responses in stages through July 2019.
The Corps is requesting an extension of the FPL Turkey Point project from April 22, 2019 until May 22, 2019. A Department of the Army permit cannot be issued until we receive: A complete mitigation plan. A request for additional information was sent to the applicant on February 26, 2019 and the applicant provided a response March 19, 2019. The Corps will need the extension to review the information and incorporate it into the record of decision. The Corps (Regulatory) cannot issue a permit until the mitigation is finalized.
Justification due to internal agency factors - in perfecting the legal land description of the ROW grant.