USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

FAST-41 Missed Date: Construction and Operations Plan

Submitted by Anonymous on

Final Required Milestone Date of 07/01/2021 for Issuance of decision for permit/approval has passed by 5 business days

Action
Project Name: Responsible Agency:
Bureau of Ocean Energy Management
Status:
In Progress
POC Name:
Isis Farmer
POC Title:
NEPA Coordinator

Description:

Before a renewable energy facility can be constructed, a lessee or applicant must submit a construction and operations plan (COP) for BOEM’s review and approval. Once submitted, BOEM conducts environmental and technical reviews of the COP and decides whether to approve, approve with modification, or disapprove the COP. Guidance on information requirements for COPs can be found at:  https://www.boem.gov/COP-Guidelines/. On March 19, 2019, Bay State Wind submitted a COP for Lease OCS-A 0500. 

Milestones:

Initial application submitted (Applicant Action)
Completed Date:
Milestone Details

The milestone is dependent upon the applicant - BOEM does not have sufficient information to establish a target completion date.

Final decision/agency action (Agency Action)
Current Target Date:
Milestone Details

The milestone is dependent upon the previous milestone - BOEM does not have sufficient information to establish a target completion date.

Milestone
Final decision/agency action (Agency Action)
Current Target Date:
Milestone Details

The milestone is dependent upon the previous milestone - BOEM does not have sufficient information to establish a target completion date.

Project

PROJECT WEBSITE: Bay State Wind

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Planned

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PLANNED

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
PENDING

0 out of 8

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects
Major Infrastructure Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of the Army

Department of the Army, US Army Corps of Engineers - Civil Works

Description:

Bay State Wind (BSW) proposes to develop, build, and operate a utility-scale offshore wind facility.  The Bay State Wind Offshore Wind Farm Project (the Project) proposes to construct up to 110 wind turbine generators (“WTG”), up to 186 miles of associated inter-array cabling, two co-located offshore substations (OSSs), export cables, and an onshore operations and maintenance (O&M) facility with an associated Base Port during the operation phase.

The Project is located in federal water on the Outer Continental Shelf (OCS), specifically in Bureau of Ocean Energy Management (BOEM) Renewable Energy Lease Area OCS-A 0500, approximately 14 miles south of Martha’s Vineyard, Massachusetts. The undersea Export Cable will traverse both federal waters and state waters of Rhode Island and Massachusetts, and ultimately making landfall within the Brayton Point Commerce Center (BPCC) located in Somerset, Massachusetts.

The Environmental Review and Permitting Status of this project will be changed to “In Progress” once the Notice of Intent to prepare an Environmental Impact Statement (EIS) has been issued.

field_status
System Comments
Final Required Milestone Date of 07/01/2021 for Issuance of decision for permit/approval has passed by 5 business days
Approver Comments
The missed date functionality was erroneously triggered due to a malfunction of the Permitting Dashboard since the project does not yet have a full and complete timetable.
Previous Action Status
New Action Status
Missed Date Process
No
Missed Date Triggered by Extension
No
New Milestone
Final decision/agency action (Agency Action)
Current Target Date:
Milestone Details

The milestone is dependent upon the previous milestone - BOEM does not have sufficient information to establish a target completion date.

Response Date