Milestone Extension: Use Authorization (DOI-BOR)
Delayed due to lapse in appropriations
Delayed due to lapse in appropriations
Applicant's consultant requested additional time to provide needed information for a complete PCN.
An outstanding item for the Department of Army's application is the 408 review which evaluates impacts to Federal projects. The applicant submitted their application for 408 review on July 17, 2018. After the 408 review is complete, the applicant will then submit the revised mitigation plan for the Corps' review. The Corps (Regulatory) cannot issue a permit until the 408 review and mitigation are finalized. USACE's original time estimation was based on when they received a complete mitigation plan from the applicant which they were submitting after the 408 review was complete.
All are aware of the changes due to federal funding lapsing. Lapse in funding required public meetings to be cancelled and the public comment period to be extended through the new public meetings. Public comment period was extended 8 weeks which puts the entire schedule back 8 weeks. We were already moving as quickly as possible and we can't continue until we have all comments received. We are working to address comments now as we can, but we anticipate new comments with the meetings which need to be addressed.
Entered on behalf of USFS/Reginal Woodruff.
The project sponsor, Idaho Power, requested in an October 26, 2018 letter to the US Forest Service to pause the special use authorization for Boardman to Hemingway project until February 2019. The request was due to potential limitations in staffing for review and signing of the special use document during the holiday season. The point of contact for the pause is M. Mark Stokes at 208-338-2483 or mstokes@idahopower.com
1. Project sponsor concurs with date change. See separate email to FERC, FPISC-OED, project sponsor and cooperating agencies. 2. see #1 above 3. It is up to FERC as lead agency to document any changes in the project's CPP. This has not been discussed at any project-specific CERPO meeting. 4. Target date for permit issuance may be "moved to the left" depending upon the date of completion of the Section 106 consultation process. 5. My agency CERPO has been made aware of the fact that the date is being changed because of the dependency factor.
Please refer to the narrative provided in support of the requested milestone change for the Baltimore District permit action.
BLM issued its Draft EIS in August 2018; FWS received a complete and sufficient Biological Assessment on October 25, 2018 and anticipated concluding consultation within the 135 days provided by statute; however, due to a lapse in appropriations the government was shut down for 35 days. FWS anticipates concluding consultation by April 15, 2019, which allows for the entire 135 days provided by statute. BLM does not anticipate issuing its FEIS until May of 2019, and its ROD in July of 2019. Issuing the BO by April 15, 2019, will not delay any other project-related actions.