Approved

Milestone Extension: Environmental Assessment (EA)

Additional time is required to issue the draft Environmental Assessment (EA) because the Project Sponsor updated the proposed installation methodology for the fiber optic cable while the EA was being developed.

Milestone Extension: Construction and Operations Plan

The project sponsor provided BOEM notice on June 26, 2023 of plans to initiate onshore construction activities. The notice provided information on their planned work at the Onshore Converter Station and laydown yards (Phase 1A activities, scheduled to start around July 10), and installation of splice vaults and duct banks, and the expansion of an existing substation (Phase 1B activities, scheduled to commence around September).

Milestone Extension: Section 408 Permit

The basis for USACE requests to extend the final completion date for the Section 408
Permit is that these actions are dependent upon the timing of BOEM’s issuance of a FEIS and ROD to conclude its NEPA review.

Milestone Extension: Section 408 Permit

The project sponsor provided BOEM notice on June 26, 2023 of plans to initiate onshore construction activities. The notice provided information on their planned work at the Onshore Converter Station and laydown yards (Phase 1A activities, scheduled to start around July 10),

Milestone Extension: NPS Permit

The project sponsor provided BOEM notice on June 26, 2023 of plans to initiate onshore construction activities. The notice provided information on their planned work at the Onshore Converter Station and laydown yards (Phase 1A activities, scheduled to start around July 10),