BOEM is requesting these completion date modifications due to the timing of the Project Sponsor’s submission of a revised Construction and Operations Plan (COP) containing additional data and assessments that BOEM requires prior to issuing a Notice of Intent (NOI) to prepare an Environmental Impact Statement (EIS) under NEPA. BOEM has requested that the revised COP contain certain survey data for one of the proposed cable routes as well as the following assessments: the Navigational Safety Risk Assessment; Historic Resources Visual Effects Assessment for certain facilities; Marine Archaeological Resource Assessment for a particular cable route; and the Terrestrial Archeological Resource Assessment for all routes and facilities in the onshore project design envelope. The Project Sponsor intends to submit the revised COP containing all the requested information on October 27, 2025. The Section 408 final completion date is dependent upon the final completion date of BOEM’s NEPA action. USACE requests a review of 90 days between issuance of the ROD and issuance of USACE’s decisions.
Cooperating under NEPA
Description:
A Section 408 Permission is required from the US Army Corps of Engineers pursuant to Section 14 of the Rivers and Harbors Act of 1899, 33 U.S.C. 408 (Section 408) and the Corps will evaluate the proposed activity relative to the nearby US Army Corps of Engineers Civil Works Projects and assets.
Milestones:
PROJECT WEBSITE: Skipjack Wind
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management
View FAST-41 Postings by Agencies
Description:
Skipjack Offshore Energy, LLC (SJOE) intends to develop, build, operate, and own (through one or more affiliated special purpose entities) an offshore wind farm located approximately 15 miles off the coast of Delaware within Lease Areas OCS A0519 and OCS A0482. The purpose of the Project is to construct and operate a new offshore wind farm designed to help one or more states within the mid-Atlantic region meet their clean energy goals. The Project would consist of up to 72 wind turbine generators (“WTG”), associated inter-array cabling, new onshore and offshore substations, transmission cables and onshore works for connection to the wholesale electric grid administered by PJM Interconnection L.L.C.
Original Target Date: 11/09/2027
Milestone: Issuance of Decision (Agency Action)
Requested extensions greater than 30 days for this Action are shown below:
Issuance of Decision (Agency Action) extended by 246
From: 11/09/2027
To: 07/12/2028