USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Milestone Extension: Endangered Species Act Consultation (DOI-FWS)

Submitted by craig.litteken… on

BOEM is requesting these completion date modifications due to the timing of the Project Sponsor’s submission of a revised Construction and Operations Plan (COP) containing additional data and assessments that BOEM requires prior to issuing a Notice of Intent (NOI) to prepare an Environmental Impact Statement (EIS) under NEPA. BOEM has requested that the revised COP contain certain survey data for one of the proposed cable routes as well as the following assessments: the Navigational Safety Risk Assessment; Historic Resources Visual Effects Assessment for certain facilities; Marine Archaeological Resource Assessment for a particular cable route; and the Terrestrial Archeological Resource Assessment for all routes and facilities in the onshore project design envelope. The Project Sponsor intends to submit the revised COP containing all the requested information on October 27, 2025.  The timing of ESA consultation with FWS is dependent on the timing of the NEPA process.  The date for receipt of a consultation request is set to be shortly after issuance of the DEIS. The remaining dates for ESA consultation flow from the date that consultation is initiated.

Action
Project Name: Responsible Agency:
Fish and Wildlife Service
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
Planned
POC Name:
Genevieve LaRouche
POC Title:
Project Leader

Milestones:

ESA Consultation Request Package Submitted (Agency Action)
Current Target Date:
FWS determines ESA Consultation Package is Complete - Formal (Agency Action)
Current Target Date:
ESA Consultation Concludes (Agency Action)
Current Target Date:
Milestone
ESA Consultation Concludes (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: Skipjack Wind

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING

0 out of 0

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Description:

Skipjack Offshore Energy, LLC (SJOE) intends to develop, build, operate, and own (through one or more affiliated special purpose entities) an offshore wind farm located approximately 15 miles off the coast of Delaware within Lease Areas OCS A0519 and OCS A0482. The purpose of the Project is to construct and operate a new offshore wind farm designed to help one or more states within the mid-Atlantic region meet their clean energy goals. The Project would consist of up to 72 wind turbine generators (“WTG”), associated inter-array cabling, new onshore and offshore substations, transmission cables and onshore works for connection to the wholesale electric grid administered by PJM Interconnection L.L.C.

field_status
System Comments
Furthest out
Original Target Date: 04/19/2027
Milestone: ESA Consultation Concludes (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

ESA Consultation Concludes (Agency Action) extended by 274
From: 04/19/2027
To: 01/18/2028
Approver Comments
Executive Director Determination signed on 3/24/25.
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
ESA Consultation Concludes (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
ESA Consultation Concludes (Agency Action)
Current Target Date: