FAST-41 Missed Date:Safe Drinking Water Act, Underground Injection Control (UIC): Issuance of final UIC permit decision
Agency Milestone Date of 07/06/2022 for Issuance of final UIC permit decision has passed by 1 business days
Agency Milestone Date of 07/06/2022 for Issuance of final UIC permit decision has passed by 1 business days
Agency Milestone Date of 06/13/2024 for Scoping (Agency Action) has passed by 1 business days
A confluence of interconnected issues has contributed to the need to revise the overall permitting timetable for this project. The dates are shifting mainly because additional ESA species surveys have been added to the biological work plan in consultation with USFWS and the cultural resource surveys need to be re-performed.
A confluence of interconnected issues has contributed to the need to revise the overall permitting timetable for this project. The dates are shifting mainly because additional ESA species surveys have been added to the biological work plan in consultation with USFWS and the cultural resource surveys need to be re-performed.
A confluence of interconnected issues has contributed to the need to revise the overall permitting timetable for this project. The dates are shifting mainly because additional ESA species surveys have been added to the biological work plan in consultation with USFWS and the cultural resource surveys need to be re-performed.
Coordination with all cooperating agencies and project sponsor has occurred for milestone schedule adjustments.
A confluence of interconnected issues has contributed to the need to revise the overall permitting timetable for this project. The dates are shifting mainly because additional ESA species surveys have been added to the biological work plan in consultation with USFWS and the cultural resource surveys need to be re-performed.
Coordination with all cooperating agencies and project sponsor has occurred for milestone schedule adjustments.
BOEM NEPA schedule was extended 119 days, so NMFS milestones adjusted accordingly.
The Project schedule provided by the proponent accounted for a delivery of a final Plan of Development to the BLM on 4 April 2025 which needed to include a NV
The ESA milestones "FWS Determines ESA Consultation Package is Complete - Formal" and "ESA Consultation Concludes" are dependent on BOEM’s EIS action milestones. A shift of BOEM’s EIS action milestones by 119 days results in a commensurate shift to these ESA action milestones. Therefore, an extension is requested based upon the extension of BOEM’s EIS milestones. The
The NPDES Permit milestones are dependent on BOEM's EIS action milestones. With the shift in the ROD date, EPA will accordingly extend the milestone date for issuance of the final decision for permit/approval of the Clean Water Act Section 402 permit. This enables EPA to ensure compliance with ESA and with other laws, such as those related to Essential Fish Habitat (EFH).