USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Milestone Extension: Environmental Impact Statement (EIS)

Submitted by cori.carraway@… on

Vineyard Northeast’s delayed submission of a complete Terrestrial Archaeological Resources Assessment (TARA) has resulted in delays to the development of the draft EIS. A complete TARA is needed to analyze impacts to cultural resources in the draft EIS and to prepare the Finding of Effect (FOE) and draft National Historic Preservation Act (NHPA) Section 106 Memorandum of Agreement (MOA) for inclusion in the draft EIS. BOEM is required to include the FOE and the draft MOA with the draft EIS to fulfill NEPA substitution standards, as BOEM is using NEPA substitution to fulfill its NHPA Section 106 obligations in accordance with 36 CFR 800.8(c). Vineyard Northeast intends to submit an updated TARA to BOEM on April 15, 2025, resulting in an 119-day delay to publication of the draft EIS and subsequent EIS action milestones. 

Action
Project Name: Responsible Agency:
Bureau of Ocean Energy Management
Status:
In Progress
POC Name:
Heather Schultz
POC Title:
NEPA Coordinator

Milestones:

Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action)
Completed Date:
Milestone Details

Prior to issuance of the Notice of Intent, BOEM will review the Construction and Operations Plan (COP) to determine whether the COP is sufficiently complete for the purposes of issuing an NOI in accordance with the NEPA regulations at 40 CFR 1501.9 and BOEM's regulations at 30 CFR part 585.

BOEM reviews the COP for consistency with its published guidance, BOEM Guidance on Information Needed for Issuance of a Notice of Intent (NOI) Under the National Environmental Policy Act (NEPA) for a Construction and Operations Plan ("NOI Checklist").

Scoping (Agency Action)
Completed Date:
Milestone Details

This milestone marks the conclusion of scoping.  

Public scoping meetings and details can be found here: https://www.boem.gov/renewable-energy/state-activities/vineyard-northeast

Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action)
Current Target Date:
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action)
Current Target Date:
Issuance of Lead Agency Record of Decision (Agency Action)
Current Target Date:
Milestone
Issuance of Lead Agency Record of Decision (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: Vineyard Offshore

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
11/09/2026

0 out of 10

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Environmental Protection Agency

Environmental Protection Agency

Description:

Vineyard Northeast proposes to construct and operate the Project located in Lease Area OCS-A 0522, which covers approximately 132,370 acres (ac) and is located approximately 31 miles from Nantucket, Massachusetts and 39 miles from Martha’s Vineyard, Massachusetts.

Offshore components of the Project will consist of up to 160 wind turbine generators (WTG) and electrical service platform (ESP) positions within the Lease Area with one nautical mile spacing between positions. The WTGs and ESPs will be supported by monopiles or piled jacket foundations.

Between the Lease Area and shore, the offshore export cables will be installed within two offshore export cable corridors (OECC), the Massachusetts OECC and the Connecticut OECC.

    • The Massachusetts OECC will travel from the northernmost tip of the Lease Area to the Horseneck Beach Landfall site in Westport, Massachusetts.
    • The Connecticut OECC will travel from the southernmost tip of the Lease Area to three potential landfall sites: Eastern Point Beach, Ocean Beach, and Niantic Beach; all near New London, Connecticut.

Onshore components of the Project will include export cable landfall areas, high-voltage direct current onshore cables, high-voltage alternating current interconnection cables, converter and booster stations, and onshore substation facilities in Massachusetts and Connecticut. 

field_status
System Comments
Furthest out
Original Target Date: 03/23/2026
Milestone: Issuance of Lead Agency Record of Decision (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

Issuance of Lead Agency Record of Decision (Agency Action) extended by 140
From: 03/23/2026
To: 08/10/2026
Approver Comments
EDD Signed 4/18/2025 granting movement
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Issuance of Lead Agency Record of Decision (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
Issuance of Lead Agency Record of Decision (Agency Action)
Current Target Date: