The Section 10/404 milestones are dependent on BOEM’s EIS action milestones. A shift of BOEM’s EIS action milestones by 119 days results in a commensurate shift to the Section 10/404 action milestones. Therefore, an extension of the Section 10/404 milestones is requested based upon the extension of BOEM’s EIS milestones.
Cooperating under NEPA
Description:
Department of Army authorization from the US Army Corps of Engineers Norfolk District is required pursuant to Section 10 of the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water Act. Activities that require authorization include: Offshore, the installation/construction of up to 205 wind turbine generators (WTGs) and three Offshore Substations. The trenching and placement of the Inter-Array Cables, and Export Cables to the proposed landing locations. Temporary ports and laydown areas will also be required. The onshore components of the project will consist of the construction of up to two Cable Landing Locations, Horizontal Directional Drilling of the Cable Landing Location(s) to a Collector Station at Naval Air Station Oceana, Interconnection Cables above or below ground from the Collector Station to the existing Onshore Fentress Substation. An aquatic resource delineation and jurisdictional determination will be performed to determine the impacts to Waters of the US.
Milestones:
-
Environmental Impact Statement (EIS)
:
Issuance of Lead Agency Record of Decision (Agency Action)
- Current Target Date: 06/14/2027 -
Section 106 Review
:
Section 106 consultation concluded (Agency Action)
- Current Target Date: 03/31/2027 -
Endangered Species Act Consultation (DOI-FWS)
:
ESA Consultation Concludes (Agency Action)
- Current Target Date: 03/22/2027 -
Endangered Species Act Consultation (NOAA-NMFS)
:
ESA Consultation Concludes (Agency Action)
- Current Target Date: 02/22/2027 -
Magnuson-Stevens Fishery Conservation and Management Act, Section 305 Essential Fish Habitat (EFH) Consultation
:
NOAA Issues any EFH Conservation Recommendations (Agency Action)
- Current Target Date: 12/23/2026
-
Environmental Impact Statement (EIS)
:
Issuance of Lead Agency Record of Decision (Agency Action)
- Current Target Date: 06/14/2027 -
Section 106 Review
:
Section 106 consultation concluded (Agency Action)
- Current Target Date: 03/31/2027 -
Endangered Species Act Consultation (DOI-FWS)
:
ESA Consultation Concludes (Agency Action)
- Current Target Date: 03/22/2027 -
Endangered Species Act Consultation (NOAA-NMFS)
:
ESA Consultation Concludes (Agency Action)
- Current Target Date: 02/22/2027 -
Magnuson-Stevens Fishery Conservation and Management Act, Section 305 Essential Fish Habitat (EFH) Consultation
:
NOAA Issues any EFH Conservation Recommendations (Agency Action)
- Current Target Date: 12/23/2026
PROJECT WEBSITE: Vineyard Offshore
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of Commerce, National Oceanic and Atmospheric Administration
Department of the Interior, Fish and Wildlife Service
Department of the Army, US Army Corps of Engineers - Regulatory
Environmental Protection Agency
Description:
Vineyard Northeast proposes to construct and operate the Project located in Lease Area OCS-A 0522, which covers approximately 132,370 acres (ac) and is located approximately 31 miles from Nantucket, Massachusetts and 39 miles from Martha’s Vineyard, Massachusetts.
Offshore components of the Project will consist of up to 160 wind turbine generators (WTG) and electrical service platform (ESP) positions within the Lease Area with one nautical mile spacing between positions. The WTGs and ESPs will be supported by monopiles or piled jacket foundations.
Between the Lease Area and shore, the offshore export cables will be installed within two offshore export cable corridors (OECC), the Massachusetts OECC and the Connecticut OECC.
-
- The Massachusetts OECC will travel from the northernmost tip of the Lease Area to the Horseneck Beach Landfall site in Westport, Massachusetts.
- The Connecticut OECC will travel from the southernmost tip of the Lease Area to three potential landfall sites: Eastern Point Beach, Ocean Beach, and Niantic Beach; all near New London, Connecticut.
Onshore components of the Project will include export cable landfall areas, high-voltage direct current onshore cables, high-voltage alternating current interconnection cables, converter and booster stations, and onshore substation facilities in Massachusetts and Connecticut.
-
Environmental Impact Statement (EIS)
:
Issuance of Lead Agency Record of Decision (Agency Action)
- Current Target Date: 06/14/2027 -
Section 106 Review
:
Section 106 consultation concluded (Agency Action)
- Current Target Date: 03/31/2027 -
Endangered Species Act Consultation (DOI-FWS)
:
ESA Consultation Concludes (Agency Action)
- Current Target Date: 03/22/2027 -
Endangered Species Act Consultation (NOAA-NMFS)
:
ESA Consultation Concludes (Agency Action)
- Current Target Date: 02/22/2027 -
Magnuson-Stevens Fishery Conservation and Management Act, Section 305 Essential Fish Habitat (EFH) Consultation
:
NOAA Issues any EFH Conservation Recommendations (Agency Action)
- Current Target Date: 12/23/2026
-
Environmental Impact Statement (EIS)
:
Issuance of Lead Agency Record of Decision (Agency Action)
- Current Target Date: 06/14/2027 -
Section 106 Review
:
Section 106 consultation concluded (Agency Action)
- Current Target Date: 03/31/2027 -
Endangered Species Act Consultation (DOI-FWS)
:
ESA Consultation Concludes (Agency Action)
- Current Target Date: 03/22/2027 -
Endangered Species Act Consultation (NOAA-NMFS)
:
ESA Consultation Concludes (Agency Action)
- Current Target Date: 02/22/2027 -
Magnuson-Stevens Fishery Conservation and Management Act, Section 305 Essential Fish Habitat (EFH) Consultation
:
NOAA Issues any EFH Conservation Recommendations (Agency Action)
- Current Target Date: 12/23/2026
Original Target Date: 06/22/2026
Milestone: Final Verification/Permit Decision Rendered (Agency Action)
Requested extensions greater than 30 days for this Action are shown below:
Final Verification/Permit Decision Rendered (Agency Action) extended by 140
From: 06/22/2026
To: 11/09/2026