FAST-41 Missed Date:Environmental Impact Statement (EIS): Scoping (Agency Action)
Agency Milestone Date of 03/17/2024 for Scoping (Agency Action) has passed by 1 business days
Agency Milestone Date of 03/17/2024 for Scoping (Agency Action) has passed by 1 business days
Agency Milestone Date of 01/31/2024 for Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) has passed by 1 business days
NTIA has determined more time is needed to prepare and finalize the document that will conclude the NEPA process and is therefore extending the final NEPA completion date. The NEPA date change impacts the timing of cooperating agency dependent actions, including the USACE Section 404 action.
NTIA has determined more time is needed to prepare and finalize the document that will conclude the NEPA process and is therefore extending the final NEPA completion date. The NEPA date change impacts the timing of cooperating agency dependent actions, including the NPS Permit action.
NTIA has determined more time is needed to prepare and finalize the document that will conclude the NEPA process and is therefore extending the final NEPA completion date. The NEPA date change impacts the timing of cooperating agency dependent actions, including the FWS right-of-way action.
NTIA has determined more time is needed to prepare and finalize the document that will conclude the NEPA process and is therefore extending the final NEPA completion date. The NEPA date change impacts the timing of cooperating agency dependent actions, including the BLM right-of-way action.
The Section 106 completion date is being modified to allow for further coordination between the Project Sponsor and Pueblos and Tribes regarding alignment of the proposed route and protection of important resources.
NTIA has determined more time is needed to prepare and finalize the document that will conclude the NEPA process and is therefore extending the final NEPA completion date.
The timing of the OCS Air Permit is planned to cover the project construction activity, anticipated in late 2027 to early 2028. The proposed milestone for the OCS Air Permit has been shifted in accordance with the proposed schedule shift for the project.
The changes to the PDE as described above will need to be analyzed and considered by USACE as part of their permitting processes. In addition, the Section 10/404 final completion date is dependent upon the final completion date of BOEM’s NEPA action. For this project, the USACE review will require 120 days between issuance of the ROD and issuance of USACE’s Section 10/404 decision. Therefore, an extension of the Section 10/404 final completion date is requested based upon the extension of the NEPA completion date.