Triggered missed date from extending Application Deemed Complete (Agency Action) within 30 days of its current target date which was 08/18/2025 and extended to 09/08/2025
Description:
In September 2020, the Coast Guard issued bridge permits approving the location and plans for five bridges across navigable waters of the United States. The permits are set to expire on September 11, 2025. The Coast Guard is expecting to receive applications for permit amendments to extend the time to commence and complete construction of the bridges.
Milestones:
Initial application received. Individual applications are required for each proposed crossing.
The USCG will issue public notices within 30 days of receiving the Initial Application, provided that all necessary information is provided. A 30-day comment period will follow.
The application can be deemed complete when all applicable information listed in the USCG Bridge Permit Application Guide have been received.
The decision is rendered within 90 days after the application is deemed complete.
The application can be deemed complete when all applicable information listed in the USCG Bridge Permit Application Guide have been received.
PROJECT WEBSITE: http://alaska-lng.com/
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/10/2025
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Pipelines
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Federal Energy Regulatory Commission
View FAST-41 Postings by Agencies
Description:
The proposed Alaska LNG Project is comprised of the following integrated and interdependent facilities: an LNG terminal in Southcentral Alaska designed to produce up to 20 million metric tons per annum of LNG; an approximately 807-mile, 42-inch diameter gas pipeline; a gas treatment plant (GTP) within the Prudhoe Bay Unit (PBU) on the North Slope; an approximately 1-mile, 60-inch diameter gas transmission line connecting the GTP to the PBU gas production facility; and an approximately 63-mile, 32-inch diameter gas transmission line connecting the GTP to the Point Thomson gas production facility. The mainline of the Alaska LNG Project would traverse over 800 miles from the GTP on the North Slope of Alaska through several boroughs before it crosses Cook Inlet and connects with the liquefaction plant and marine terminal in Nikiski, Alaska.
The project was initially determined to be a FAST-41 covered project in 2017. As represented in the permitting timetable, the federal environmental review and authorization process for the project was originally completed in 2020, and the project was marked as complete on the Permitting Dashboard. After the Department of Energy (DOE) granted a request for rehearing of a final order in 2021, the project was reopened on the Permitting Dashboard to include DOE’s preparation of a supplemental Environmental Impact Statement (EIS). Following the issuance of the supplemental EIS, DOE issued an updated order, and the project was marked as complete on the Permitting Dashboard in 2023.
On February 26, 2025, the project sponsor submitted a notice seeking to reinitiate FAST-41 coverage for updated Biological Opinions (under the Endangered Species Act) and renewed authorizations that are needed for the project. On March 12, 2025, it was determined that the project continues to qualify for FAST-41 coverage. Corresponding updates to the permitting timetable were posted on May 9, 2025.
The application can be deemed complete when all applicable information listed in the USCG Bridge Permit Application Guide have been received.