Milestone Extension: Lease of Power Privilege (DOI-BOR)

Submitted by georgeann.smal… on

  Because the Commission’s milestone target dates, including those for issuance of the draft and final NEPA documents and order, were modified to account for the additional time needed for the project sponsor to file required information, dependent milestone target dates are being modified accordingly.  The Commission’s request for an Executive Director determination includes additional information.

Action
Project Name: Responsible Agency:
Bureau of Reclamation
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
In Progress
POC Name:
Brad Cannon
POC Title:
Supervisory Natural Resource Specialist
POC Email:

Description:

A Lease of Power Privilege will be needed prior to any Reclamation asset being used for non-Federal power generation.

Milestones:

Completed application received (Agency Action)
Completed Date:
Issuance of Preliminary Lease (Agency Action)
Completed Date:
Issuance of the Lease of Power Privilege Contract (Agency Action)
Current Target Date:
Milestone Details

The Lease of Power Privilege is dependent on a FEIS/ROD being issued that adequately addresses Reclamation’s action.

Milestone
Issuance of the Lease of Power Privilege Contract (Agency Action)
Current Target Date:
Milestone Details

The Lease of Power Privilege is dependent on a FEIS/ROD being issued that adequately addresses Reclamation’s action.

Project

PROJECT WEBSITE: https://www.seminoepumpedstorage.com

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
11/22/2027

2 out of 7

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Energy Storage

SECTOR
Energy Storage

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Federal Energy Regulatory Commission

LEAD AGENCY
Federal Energy Regulatory Commission

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of the Interior

Department of the Interior, Bureau of Reclamation

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of the Interior

Department of the Interior, Bureau of Land Management

Description:

The proposed 972-megawatt project would use the Bureau of Reclamation's existing Seminoe Reservoir on the North Platte River in Carbon County, Wyoming, as a lower reservoir and include the construction of a new upper reservoir; two 30-mile-long, 500-kilovolt transmission lines; and other project facilities.  The proposed project facilities would primarily be located on Bureau of Land Management lands.

Update: 

The Executive Director granted Federal Energy Regulatory Commission's request to extend the Section 404 (USACE), ESA (FWS), Lease of Power Privilege (BOR), and Right-of-Way Authorization (BLM) completion dates on July 28, 2023. The Executive Director determination is posted here.

The Executive Director granted Federal Energy Regulatory Commission's request to extend the Section 404 (USACE), ESA (FWS), Lease of Power Privilege (BOR), and Right-of-Way Authorization (BLM) completion dates on September, 2024. The Executive Director determination is posted here.

field_status
System Comments
Furthest out
Original Target Date: 08/20/2025
Milestone: Issuance of the Lease of Power Privilege Contract (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

Issuance of the Lease of Power Privilege Contract (Agency Action) extended by 513
From: 12/18/2026
To: 01/15/2027
Approver Comments
EDD dated July 18, 2025
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Issuance of the Lease of Power Privilege Contract (Agency Action)
Current Target Date:
Milestone Details

The Lease of Power Privilege is dependent on a FEIS/ROD being issued that adequately addresses Reclamation’s action.

Furthest Original Target Date Milestone
Issuance of the Lease of Power Privilege Contract (Agency Action)
Current Target Date:
Milestone Details

The Lease of Power Privilege is dependent on a FEIS/ROD being issued that adequately addresses Reclamation’s action.