FAST-41 Missed Date:Magnuson-Stevens Fishery Conservation and Management Act, Section 305 Essential Fish Habitat (EFH) Consultation: NOAA determines EFH Assessment is Complete (Agency Action)

Submitted by Anonymous on

Agency Milestone Date of 08/08/2025 for NOAA determines EFH Assessment is Complete (Agency Action) has passed by 1 business days

Action
Project Name: Responsible Agency:
National Oceanic and Atmospheric Administration
Agency Status: Cooperating under FAST-41
Status:
Planned
POC Name:
Luke Byker
POC Title:
Marine Habitat Resource Specialist

Milestones:

EFH Consultation Request Submitted – EFH Assessment (Agency Action)
Completed Date:
NOAA determines EFH Assessment is Complete (Agency Action)
Current Target Date:
NOAA Issues any EFH Conservation Recommendations (Agency Action)
Current Target Date:
Milestone
NOAA determines EFH Assessment is Complete (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: https://www.nanabroadband.com/

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/15/2026

8 out of 8

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Broadband

SECTOR
Broadband

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of Commerce

LEAD AGENCY
Department of Commerce, National Telecommunications and Information Administration

View FAST-41 Postings by Agencies

Description:

The NANA Regional Corporation, Inc. proposes to implement a high-speed broadband network in the NANA region through the Tribal Broadband Connectivity Program. The proposed ~725-mile fiber optic cable route consists of a combination of terrestrial ground-laid, subsea, trenched, and aerial cable to connect villages across vast distances to the broadband Point of Presence in Kotzebue. The Project plans to bring a fiber-based broadband network capable of providing high-speed internet services to Alaska Native Villages in the NANA Region.

field_status
System Comments
Agency Milestone Date of 08/08/2025 for NOAA determines EFH Assessment is Complete (Agency Action) has passed by 1 business days
Approver Comments
Project Sponsor submitted the EFH Assessment on 8/8/25 - preventing NOAA from meeting the milestone CTD.  NOAA determined that the EFH Assessment is complete on 8/11/25. Nonconformance exempted.
Previous Action Status
New Action Status
Missed Date Process
No
Missed Date Triggered by Extension
No
New Milestone
NOAA determines EFH Assessment is Complete (Agency Action)
Current Target Date:
Response Date