FAST-41 Missed Date:Section 408 Permit: Completeness Determination (Agency Action)

Submitted by Anonymous on

Agency Milestone Date of 08/15/2025 for Completeness Determination (Agency Action) has passed by 1 business days

Action
Project Name: Responsible Agency:
US Army Corps of Engineers - Section 408
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
Planned
POC Name:
Brad Crosson
POC Title:
Section 408 Coordinator

Description:

A section 408 permit will be required for boring underneath the Rio Grande at Isleta and boring under a water conveyance structure at Escondida. 

Milestones:

Initial application submitted (Applicant Action)
Completed Date:
Completeness Determination (Agency Action)
Current Target Date:
Complete application submitted (Applicant Action)
Current Target Date:
Issuance of Decision (Agency Action)
Current Target Date:
Milestone
Completeness Determination (Agency Action)
Current Target Date:
Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/31/2026

3 out of 9

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Broadband

SECTOR
Broadband

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of Commerce

LEAD AGENCY
Department of Commerce, National Telecommunications and Information Administration

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of the Interior

Department of the Interior, Bureau of Land Management

Department of the Interior

Department of the Interior, National Park Service

Department of the Interior

Department of the Interior, Bureau of Indian Affairs

Department of the Army

Department of the Army, US Army Corps of Engineers - Section 408

Description:

The Pueblo Education Network builds middle mile broadband infrastructure for tribes, enabling digital economy participation and effectuating last-mile internet access to homes and anchor institutions and tribal businesses. The Pueblo Education Network also creates a private education network connecting tribal PreK-20 schools and libraries to each other and to national research and education networks, modernizing Indian Education in the global information age.  The overall footprint is approximately 324 miles. The project originates in Albuquerque, New Mexico and travels through Isleta Pueblo, Acoma Pueblo, and Zuni Pueblo lands with the fiber path ending at the Zuni Elementary School, Zuni Head Start Building, Zuni Governor’s Office, and Zuni High School.  The fiber path will primarily be immediately adjacent to already established roads and will travel through private lands, Bureau of Land Management, US Forest Service, New Mexico State Land Office, Navajo Nation lands at Ramah, and Zuni Pueblo lands.

The Executive Director granted a National Telecommunications and Information Administration (NTIA), request to extend the NEPA; Section 106; Right-of-Way (BLM); NPS Permit; Right-of-Way (FWS Sevilleta NWR); ESA-FWS; Section 404 final completion dates on December 28, 2023. The Executive Director determination is posted here.

The Executive Director granted a National Telecommunications and Information Administration (NTIA), request to extend the NEPA; Section 106; Right-of-Way (BLM); NPS Permit; Right-of-Way (FWS Sevilleta NWR); Section 404 final completion dates on March 28, 2024. The Executive Director determination is posted here.

The Executive Director granted a National Telecommunications and Information Administration (NTIA), request to extend the Right-of-Way (BIA) final completion date on June 26, 2024. The Executive Director determination is posted here.

The Executive Director granted a National Telecommunications and Information Administration (NTIA), request to extend the NEPA; Section 106; NPS Permit; Right-of-Way (FWS); Right-of-Way (BLM); Right-of-Way (BIA Southern Pueblos Agency); Right-of-Way (BIA Zuni Agency); USACE Section 404 final completion date on July 15, 2024. The Executive Director determination is posted here.

The Executive Director granted a National Telecommunications and Information Administration (NTIA) request to extend the NEPA; Section 106; NPS Permit; Right-of-Way (FWS); Right-of-Way (BLM); Right-of-Way (BIA Southern Pueblos Agency); Right-of-Way (BIA Zuni Agency); USACE Section 404 final completion date on December 12, 2024. The Executive Director determination is posted here.

field_status
System Comments
Agency Milestone Date of 08/15/2025 for Completeness Determination (Agency Action) has passed by 1 business days
Approver Comments
USACE completed this milestone 2 days ahead of the current schedule. However, the dashboard functionality is experiencing glitches that are preventing USACE, NTIA, and the Permitting Council from marking the milestone complete. The milestone will be marked complete as soon as the dashboard error is fixed.
Previous Action Status
New Action Status
Missed Date Process
No
Missed Date Triggered by Extension
No
New Milestone
Completeness Determination (Agency Action)
Current Target Date:
Response Date