FAST-41 Missed Date:Environmental Assessment (EA): Determination to prepare an Environmental Assessment (EA) (Agency Action)

Submitted by Anonymous on

Agency Milestone Date of 06/26/2025 for Determination to prepare an Environmental Assessment (EA) (Agency Action) has passed by 1 business days

Action
Project Name: Responsible Agency:
Bureau of Reclamation
Status:
Planned
POC Name:
Cianna Wyshnytzky
POC Title:
Project Manager, Columbia Pacific Northwest Regional Office

Description:

Reclamation plans to analyze the effects of authorizing the project by preparing an environmental assessment, pursuant to the National Environmental Policy Act.

Milestones:

Determination to prepare an Environmental Assessment (EA) (Agency Action)
Current Target Date:
Issuance of a Draft EA / Release for Public Review (Agency Action)
Current Target Date:
Issuance of a Final EA (Agency Action)
Current Target Date:
EA Process Concluded (Agency Action)
Current Target Date:
Milestone
Determination to prepare an Environmental Assessment (EA) (Agency Action)
Current Target Date:
Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/28/2028

0 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Electricity Transmission

SECTOR
Electricity Transmission

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Reclamation

View FAST-41 Postings by Agencies

Description:

Clearway Energy Group requests a land use authorization license from the Bureau of Reclamation to construct, operate, and maintain electrical power transmission lines and associated access roads on Reclamation-administered land.  The 230-kilovolt electrical power transmission line would transmit electricity from a solar power generation facility on private land, across Reclamation-administered land, to the Vantage Substation in Grant County, Washington. This Project will serve electricity users in Washington, with the target of serving Grant County specifically. 

 
 
 
field_status
System Comments
Agency Milestone Date of 06/26/2025 for Determination to prepare an Environmental Assessment (EA) (Agency Action) has passed by 1 business days
Approver Comments
Milestone is complete - BOR failed to mark complete when inputting the initial permitting timetable.
Previous Action Status
New Action Status
Missed Date Process
No
Missed Date Triggered by Extension
No
New Milestone
Determination to prepare an Environmental Assessment (EA) (Agency Action)
Current Target Date:
Response Date
Reporting Agency