USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Milestone Extension: Use Authorization (DOI-BOR)

Submitted by giannina.dimai… on

A confluence of interconnected issues has contributed to the need to revise the overall permitting timetable for this project. The dates are shifting mainly because additional ESA species surveys have been added to the biological work plan in consultation with USFWS and the cultural resource surveys need to be re-performed.

Coordination with all cooperating agencies and project sponsor has occurred for milestone schedule adjustments. 

Action
Project Name: Responsible Agency:
Bureau of Reclamation
Agency Status: Cooperating under FAST-41
Status:
Planned
POC Name:
Chris Walls
POC Title:
Chief of Resources

Milestones:

Initial application submitted (Applicant Action)
Completed Date:
Application deemed complete (Agency Action)
Current Target Date:
Final decision/agency action (Agency Action)
Current Target Date:
Milestone
Final decision/agency action (Agency Action)
Current Target Date:
Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE

0 out of 5

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of the Interior

Department of the Interior, Bureau of Reclamation

Description:

Intersect Power proposes to construct, operate, maintain, and eventually decommission a 1,150 megawatt solar photovoltaic facility and battery energy storage system on public lands administered by the U.S. Bureau of Land Management (BLM) and Bureau of Reclamation, as well as private lands. The project boundary includes 7,294.5 total acres of which approximately 6,021.2 acres would be developed as part of the solar facility.  The BLM lands where the project is proposed are designated by the BLM as renewable energy “development focus areas” in the Desert Renewable Energy Conservation Plan. The Project’s primary goal is to contribute to the achievement of California’s renewable energy goals and create a new point of interconnection for renewable energy in the Imperial Valley. The project is located in Imperial County, California approximately 37 miles southeast of the Salton Sea and 1.2 miles north of the U.S-Mexico border.  BLM is the lead federal agency.

 

field_status
System Comments
Furthest out
Original Target Date: 04/03/2026
Milestone: Final decision/agency action (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

Final decision/agency action (Agency Action) extended by 346
From: 04/03/2026
To: 03/15/2027
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Final decision/agency action (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
Final decision/agency action (Agency Action)
Current Target Date: