FAST-41 Missed Date:Safe Drinking Water Act, Underground Injection Control (UIC): Issuance of final UIC permit decision

Submitted by Anonymous on

Agency Milestone Date of 07/06/2022 for Issuance of final UIC permit decision has passed by 1 business days

Milestone
Issuance of final UIC permit decision
Current Target Date:
Project

PROJECT WEBSITE: Lisbon Valley Mining Company Plan Modification

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/29/2026

0 out of 6

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Mining

SECTOR
Mining

transparency icon

CATEGORY
Project Category FAST-41 Transparency Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Environmental Protection Agency

Environmental Protection Agency

Description:

Lisbon Valley Mining Company, LLC (LVMC) currently mines copper ore from an open pit mine on 4,480 acres in San Juan County, Utah. LVMC submitted a Plan of Operations Modification to the Bureau of Land Management to expand open pit and beneficiation operations, and to initiate the extraction of copper through a method of in-situ recover into an adjoining area. Additions would include a new open pit, waste rock storage area, process ponds, and in-situ recovery wells in a proposed 5,430 acres. Estimated surface disturbance contained in the Plan of Operations Modification is 1,190 acres. In addition to BLM’s analysis, the project would also require a pending aquifer exemption from the Environmental Protection Agency to allow fluids to be injected underground for the in-situ recovery process.

This project is posted in the interest of transparency and response to Executive Order 14241. 

field_status
System Comments
Agency Milestone Date of 07/06/2022 for Issuance of final UIC permit decision has passed by 1 business days
Approver Comments
Transparency Project - Not subject to FAST-41 Nonconformance Protocol
Previous Action Status
New Action Status
Missed Date Process
No
Missed Date Triggered by Extension
No
New Milestone
Issuance of final UIC permit decision
Current Target Date:
Response Date
Reporting Agency