Milestone Extension: Section 10 Rivers and Harbors Act of 1899 and Section 404 Clean Water Act

Submitted by carlos_arandia on

We did not previously have a target date for our target completion date (our 4th and last milestone), or target dates for our 2nd and 3rd milestones, so there is nothing to extend beyond 30 days. As such, I am not sure why this notification is popping up. I marked the "reason for change" date as "Updating Planned Date". I was under the impression from the last Dashboard Administrator meeting that updating planned dates do not require FPISC OED review, even if planned completion dates would be extended more than 30 days. It would be very helpful to get clarification on this. Regardless, we did not have target dates for our 2nd, 3rd, and 4th milestones previously because we erroneously thought we did not need target dates for all our milestones when we were in "planned" status. As such, there is no target completion date for us to modify or extend. That being said, our planned target completion date of 2/6/2020 is in the description of our final target milestone that is currently published on the Dashboard - we simply added it this date as our target completion date and are asking for approval. We have coordinated with the applicant/project sponsor on the target end date and requirements to meet the target end date. Thank you!

Milestone
Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: http://alaska-lng.com/

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/13/2023

14 out of 14

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Pipelines

SECTOR
Pipelines

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Federal Energy Regulatory Commission

LEAD AGENCY
Federal Energy Regulatory Commission

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of Homeland Security

Department of Homeland Security, US Coast Guard

Department of the Interior

Department of the Interior, Bureau of Land Management

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of Energy

Department of Energy, Office of Fossil Energy

Department of the Interior

Department of the Interior, National Park Service

Department of Energy

Department of Energy

Description:

The Alaska LNG Project is comprised of the following integrated and interdependent facilities:  a liquefied natural gas (LNG) terminal in Southcentral Alaska designed to produce up to 20 million metric tons per annum of LNG; an approximately 807-mile, 42-inch diameter gas pipeline; a gas treatment plant (GTP) within the Prudhoe Bay Unit (PBU) on the North Slope; an approximately 1-mile, 60-inch diameter gas transmission line connecting the GTP to the PBU gas production facility; and an approximately 63 mile, 32-inch diameter gas transmission line connecting the GTP to the Point Thomson gas production facility.  The mainline of the Alaska LNG Project will traverse over 800 miles from the GTP on the North Slope of Alaska through several boroughs before it crosses Cook Inlet and connects with the liquefaction plant and marine terminal in Nikiski, Alaska. 

Fast-41 Initiation Notice

Project Application and Supporting Documents

Federal Agency Actions

FERC Litigation

  • None filed.

 

For improved transparency, FERC is providing this supplemental table to reflect the additional federal authorizations that may be required for the Alaska LNG Project.  

Additional Federal Agency Permitting Timetable for the Alaska LNG Project 
Responsible Agency Federal Permit/Review Status Applicable Timelines
US Coast Guard Letter of Recommendation Complete Receipt of Letter of Intent:  May 15, 2014
Receipt of Waterway Suitability Assessment:  March 18, 2016
Letter of Recommendation to FERC:  August 17, 2016

 

Last updated September 16, 2020

field_status
System Comments
Furthest out Original Target Date: 04/14/2017
Milestone: Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received

Requested extensions greater than 30 days for this Action are shown below:

Complete Pre-Construction Notification (PCN)/Application Received by 908 days
From: 12/31/1969
To: 10/09/2019

Publication of Public Notice by 923 days
From: 12/31/1969
To: 10/24/2019

Final Verification/Permit Decision Rendered by 1028 days
From: 12/31/1969
To: 02/06/2020
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action)
Current Target Date: