USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Portions of this site may be affected due to a lapse in appropriations and associated shutdown/furloughs. Please monitor this page for updates on site availability and operating status.

Milestone Extension: Section 408 Permit

Submitted by carlos_arandia on

The reason for the date changes was because of the unknown FERC DEIS and FEIS projected release dates. Once those dates were known, the Portland District worked with the applicant on new 408 decision dates. The applicant concurred with the new dates. The date changes coincide with the FERC EIS schedule dates. CERPR has been made aware of the date changes and an email was sent to all interested parties and no objection was received.

Milestone
Issuance of Decision (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: Jordan Cove LNG

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Paused

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PAUSED

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE

9 out of 9

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Pipelines

SECTOR
Pipelines

Project Category

CATEGORY
Project Category FAST-41 Covered Projects
Major Infrastructure Projects

Federal Energy Regulatory Commission

LEAD AGENCY
Federal Energy Regulatory Commission

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of Energy

Department of Energy, Office of Fossil Energy

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

The Jordan Cove LNG Project (Docket No. CP17-495-000) includes the construction and operation of a liquefied natural gas (LNG) export terminal on the North Spit of Coos Bay in Coos County, Oregon.  The terminal would include gas inlet facilities, a metering station, a gas conditioning plant, five liquefaction trains and associated equipment, two full-containment LNG storage tanks, an LNG transfer line, LNG ship loading facilities, a marine slip, a marine offloading facility, a new access channel between the Coos Bay Navigation Channel and the new marine slip, and enhancements to the existing Coos Bay Navigation Channel at four turns.  In addition, the terminal would include emergency and hazard, electrical, security, control, and support systems, administrative buildings, and a temporary workforce housing facility.  The LNG terminal would be designed to liquefy about 1.04 billion cubic feet per day of LNG for export to markets across the Pacific Rim.

The Pacific Connector Gas Pipeline (Docket No. CP-17-494) includes the construction and operation an approximately 229-mile-long, 36-inch-diameter interstate natural gas transmission pipeline and associated aboveground facilities.  The pipeline would originate near Malin in Klamath County, Oregon, traverse Douglas and Jackson Counties, and terminate (at the LNG Terminal) in Coos County, Oregon.  The pipeline would be capable of transporting about 1.2 billion cubic feet per day of natural gas.  The associated aboveground facilities would include the new Klamath Compressor Station (61,500 horsepower) near Malin, Oregon; 3 new meter stations; 5 new pig launchers and receivers; 17 mainline block valves; and a gas control communication system.

On May 10, 2021, the project sponsors filed a letter with the Commission stating that they are pausing the development of the project.

Fast-41 Initiation Notice

Project Application and Supporting Documents

Federal Agency Actions

FERC Litigation

  • None filed.

 

For improved transparency, FERC is providing this supplemental table to reflect the additional federal authorizations that may be required for the Jordan Cove LNG Project.  

Additional Federal Agency Authorization Timetable for the Jordan Cove LNG and Pacific Connector Gas Pipeline Project
Agency Permit Status Applicable Timelines
U.S. Coast Guard Letter of Recommendation Completed Receipt of Letter of Intent:  April 2006
Receipt of Water Suitability Assessment:  10/1/17
Letter of Recommendation to FERC:  5/10/18  

 

Last updated June 18, 2021

field_status
System Comments
Furthest out Original Target Date: 09/15/2017
Milestone: Initial application received

Requested extensions greater than 30 days for this Action are shown below:

Completed application received by 714 days
From: 12/31/1969
To: 08/30/2019

Issuance of decision for permit/approval by 805 days
From: 12/31/1969
To: 11/29/2019
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Issuance of Decision (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
Initial application submitted (Applicant Action)
Current Target Date: