FAST-41 Missed Date: Section 404 Clean Water Act
Final Required Milestone Date of 05/22/2020 for Final Verification/Permit Decision Rendered has passed by 5 business days
Final Required Milestone Date of 05/22/2020 for Final Verification/Permit Decision Rendered has passed by 5 business days
Final Required Milestone Date of 05/12/2020 for Section 106 consultation concluded has passed by 5 business days
Final Required Milestone Date of 05/08/2020 for Issuance of Lead Agency Record of Decision has passed by 5 business days
Triggered missed date from extending Conclusion of ESA Consultation within 30 days of its current target date which was 11/12/2019 and extended to 05/23/2021
Triggered missed date from extending Conclusion of ESA Consultation within 30 days of its current target date which was 01/24/2020 and extended to 07/08/2021
Triggered missed date from extending NOAA Issues any EFH conservation recommendations within 30 days of its current target date which was 10/30/2019 and extended to 06/07/2021
Triggered missed date from extending Section 106 consultation concluded within 30 days of its current target date which was 01/24/2020 and extended to 10/20/2021
Triggered missed date from extending Issuance of Lead Agency Record of Decision within 30 days of its current target date which was 01/24/2020 and extended to 10/20/2021
Triggered missed date from extending Final Verification/Permit Decision Rendered within 30 days of its current target date which was 04/24/2020 and extended to 01/18/2022
Triggered missed date from extending Final Verification/Permit Decision Rendered within 30 days of its current target date which was 04/24/2020 and extended to 01/18/2022