Milestone Extension: Fish and Wildlife Coordination Act Review
1. No; 2. This date was provided as part of the coordinated effort with the Sponsor and all agencies in order to revise the schedule so that we could take the project out of "pause". 3. Yes, I believe all levels of management are aware of all changes being made to the schedule. 4. This date change is part of multiple date changes occurring on this project. This date change was not the impetus behind the delays to the project. This date change is in response to those delays. 5. Yes, extensively Additional Info: I'm currently working on updating all Actions/Milestone dates.