Milestone Extension: Environmental Impact Statement (EIS)
CURRENT STATUS: The Corps is working with the EIS contractor to complete studies necessary for the integrated Regulatory and 408 Draft Environmental Impact Statement. The delay in receiving the information from PCCA, which was requested in April 2020, and subsequent required sequential modelling has delayed the overall project schedule 12 months.