USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Portions of this site may be affected due to a lapse in appropriations and associated shutdown/furloughs. Please monitor this page for updates on site availability and operating status.

Milestone Extension: Environmental Impact Statement (EIS)

Submitted by carlos_arandia on

On February 27, 2018, Commission staff paused this action because it required additional information to fully assess safety impacts in the Environmental Impact Statement. As of May 18, 2018, Commission staff had received sufficient additional information and issued a Notice of Revised Schedule for completing the NEPA review, and was able to unpause this action. FERC staff consulted with the other agencies and the project sponsor for the revised target dates to complete NEPA.

Milestone
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action)
Current Target Date:
Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/05/2019

8 out of 8

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Pipelines

SECTOR
Pipelines

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Federal Energy Regulatory Commission

LEAD AGENCY
Federal Energy Regulatory Commission

Other Agencies with Actions or Authorizations:

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of Energy

Department of Energy, Office of Fossil Energy

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Description:

This project consists of two proposals:  Venture Global Calcasieu Pass Terminal (Docket No. CP15-550-000) and TransCameron Pipeline (Docket Nos. CP15-551-000 and CP15-551-001).  The project consists of:  (1) the addition of 1.4 Bcf/d through construction of a new LNG export terminal in Louisiana; and (2) construction of a 23.4-mile-long natural gas pipeline and associated meter station in Louisiana, to provide 1.9 Bcf/d of natural gas transportation service at the LNG terminal for export.

Project Application and Supporting Documents

Federal Agency Actions

FERC Litigation

  • None filed. 

 

State Agency Permitting Timetable for Venture Global Calcasieu Pass Terminal and TransCameron Pipeline Project 
Responsible State Agency Federal Permit/Review Intermediate Completion Date Final Completion Date Description Field
Louisiana Department of Natural Resources, Office of Coastal Management Section 307 CZMA Review N/A TBD The state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016) provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."
Louisiana Department of Environmental Quality, Water Permits Division Section 401 CWA Review - Water Quality Certification N/A TBD The state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable.  Water quality certification issued within 90 days after application is determined to be administratively complete.
Louisiana Department of Environmental Quality, Water Permits Division Section 402 CWA Review - National Pollutant Discharge Elimination System, Stormwater General Permit N/A TBD The state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable.  Per state regulations, the Louisiana Department of Environmental Quality (LDEQ) has 300 days from receipt of an application to review and issue a water discharge permit.  LDEQ follows the 300 day timetable for review and issuance of water discharge permits.
Louisiana Department of Environmental Quality, Water Permits Division Section 402 CWA Review - National Pollutant Discharge Elimination System, Industrial Wastewater Discharge Permit N/A TBD The state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable.  Per state regulations, the Louisiana Department of Environmental Quality (LDEQ) has 300 days from receipt of an application to review and issue a water discharge permit.  LDEQ follows the 300 day timetable for review and issuance of water discharge permits.
Louisiana Department of Environmental Quality, Water Permits Division Section 402 CWA Review - National Pollutant Discharge Elimination System, Hydrostatic Test Discharge Permit N/A TBD The state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable.  Per state regulations, the Louisiana Department of Environmental Quality (LDEQ) has 300 days from receipt of an application to review and issue a water discharge permit.  LDEQ follows the 300 day timetable for review and issuance of water discharge permits.
Louisiana Department of Environmental Quality, Air Permits Division Title V CAA Review - Operating Permit for Air Emissions N/A TBD The state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016) provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."

 

 

Last updated March 7, 2019

field_status
System Comments
Official Notice of Availability of a Final EIS published in the Federal Register milestone extended 85 days over the current final milestone target completion date
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action)
Current Target Date: