Milestone Extension: Construction and Operations Plan
This new schedule accommodates the later submission of the initial MMPA permit application.
This new schedule accommodates the later submission of the initial MMPA permit application.
This new schedule accommodates the later submission of the initial MMPA permit application.
This new schedule accommodates the later submission of the initial MMPA permit application.
New Project information was submitted by the project sponsor on October 4, 2022, October 14, 2022, and October 27, 2022 in response to stakeholder concerns which included an updated Construction and Operations Plan (COP) and permit applications showing a shift to the location of the BL England substation to an ad
The revised Section 106 technical reports, revised Finding of Effect, and revised Memorandum of Agreement (MOA) were distributed to consulting parties on November 11, 2022 for a 30-day review. On December 12, 2022, BOEM received comments that will require additional revisions to the Finding of Effect and MOA and subsequent consulting party review of those documents.
Triggered missed date from extending Completeness Determination (Agency Action) within 30 days of its current target date which was 01/30/2023 and extended to 02/20/2026
Agency Milestone Date of 01/16/2023 for FWS determines ESA Consultation Package is Complete - Formal (Agency Action) has passed by 1 business days
Agency Milestone Date of 01/16/2023 for FWS determines ESA Consultation Package is Complete - Formal (Agency Action) has passed by 1 business days
Agency Milestone Date of 01/16/2023 for FWS determines ESA Consultation Package is Complete - Formal (Agency Action) has passed by 1 business days