Milestone Extension: Outer Continental Shelf (OCS) Air Permit

Submitted by cori.carraway@… on

The new schedule accommodates the timing of offshore surveys and the submission of additional information needed for the NEPA process and environmental permitting.

Action
Project Name: Responsible Agency:
Environmental Protection Agency
Status:
Planned

Description:

The EPA promulgated the Outer Continental Shelf (OCS) air regulations (40 CFR part 55) pursuant to Section 328 of the Clean Air Act (CAA). OCS permits contain various requirements including preconstruction permit requirements under the New Source Review (NSR) permitting program and operating permit requirements under the Title V permitting program. OCS permits also include New Source Performance Standards (NSPS), National Emissions Standards for Hazardous Air Pollutants (NESHAPS) and/or state and local air pollution control requirements for sources locating within 25 miles of a state’s seaward boundary (the line 3 nautical miles distant from a state’s coastline (9 nautical miles for Texas and Florida)). OCS permit issuance is a federal action that triggers EPA obligations under other federal statutes (e.g., National Historic Preservation Act (NHPA), Endangered Species Act (ESA), Magnuson-Stevens Fishery Conservation and Management Act (MSA)). The Bureau of Ocean and Energy Management (BOEM) is the lead Federal agency for ensuring compliance with ESA, MSA and NHPA. EPA is a co-action agency for all ESA, MSA and NHPA compliance activities associated with wind development projects on the Atlantic OCS. OCS permits are issued by EPA regional offices or delegated state and local permitting authorities. To date, the EPA has delegated the OCS permitting program to three states (Delaware, Maryland and Virginia) and four permitting authorities in California (San Luis Obispo County Air Pollution Control District (APCD), Santa Barbara County APCD, South Coast Air Quality Management District and Ventura County APCD).

Once an OCS permit application is determined complete by the applicable permitting authority, the permitting authority develops and issues a draft OCS permit. This draft OCS permit is open for public comment, usually for a 30-day public comment period, and after comments are evaluated, a response to comments document is developed. Public notice documents can be found on the applicable permitting authority website.

Although EPA’s OCS air permitting projects are not subject to the National Environmental Policy Act (NEPA), the EPA actively participates in BOEM's processes under NEPA for each of the OCS projects off the Atlantic coast and considers BOEM’s environmental analyses, including the NEPA Record of Decision (ROD), in the development of the OCS air permit for each source. The ROD explains BOEM’s decision under NEPA, the alternatives BOEM considered and BOEM’s plans for mitigation and monitoring, if necessary. EPA’s final permit decision occurs after the issuance of the ROD, which fulfills EPA’s statutory obligations under ESA, MSA and NHPA. The final permit must be issued no later than one year from the date EPA determines that the OCS permit application is complete. OCS permit application submission and review milestones are discussed in more detail below.

Milestones:

NOI to apply for an Air Permit submitted (Applicant Action)
Current Target Date:
OCS Air Permit application submitted (Applicant Action)
Current Target Date:
OCS Air Permit application complete (Applicant Action)
Current Target Date:
Issuance of final decision/permit approval (Agency Action)
Current Target Date:
Milestone
Issuance of final decision/permit approval (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: http://www.KittyHawkOffshore.com

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/14/2028

0 out of 10

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of the Army

Department of the Army, US Army Corps of Engineers - Civil Works

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Environmental Protection Agency

Environmental Protection Agency

Description:

Update: In June 2022, the project name changed from Kitty Hawk Wind Project to Kitty Hawk South Wind Project to reflect the segmenting of the project.

Kitty Hawk Wind, LLC proposes to construct, own, and operate the Kitty Hawk South Offshore Wind Project. The Project will be located in the designated Renewable Energy Lease Area OCS-A 0508 (Lease Area). The Commercial Lease of Submerged Lands for Renewable Energy Development on the Outer Continental Shelf of Lease Area OCS-A 0508 was awarded through the BOEM competitive renewable energy lease auction of the Wind Energy Area offshore of North Carolina. The Lease Area covers 49,536 hectares (ha) and is located 44 kilometers (km) offshore of Corolla, North Carolina.

At this time, the Company is proposing to develop the Kitty Hawk South Offshore Wind Project in the eastern portion of the Lease Area (33,768 ha; referred to as the Wind Development Area), located approximately 61 km east of Corolla, North Carolina and approximately 54 km northeast of Kill Devil Hills, North Carolina. The offshore components of the Project, including the WTGs, offshore substations, and inter-array cables, will be located in federal waters within the Lease Area. The offshore export cable corridor will traverse both federal waters and state territorial waters of Virginia and/or North Carolina. Onshore Project components, including the export cable landfall location(s), onshore export and interconnection cables, and onshore electrical facilities, will be located in one or more of the following:

• City of Virginia Beach, Virginia;
• Dare County, North Carolina;
• Carteret County, North Carolina; and
• Craven County, North Carolina.

A COP for the Project, which includes detailed assessments of environmental, cultural, and historic resources, was submitted to BOEM on April 14, 2022.
Additional Project information is located at www.KittyHawkOffshore.com.

field_status
System Comments
Furthest out
Original Target Date: 12/30/2025
Milestone: Issuance of final decision/permit approval (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

Issuance of final decision/permit approval (Agency Action) extended by 806
From: 12/30/2025
To: 03/15/2028
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Issuance of final decision/permit approval (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
Issuance of final decision/permit approval (Agency Action)
Current Target Date: