Approved

Milestone Extension: Section 408 Permit

The applicant had initially requested a review schedule for their Kitty Hawk South project with an early NOI coming in October 2022 with the DEIS NOA occurring much later in 2024 - this timeframe has been extended, with an NOA date in Feb 2026 and a ROD date in Jan 2027.  USACE milestones were adjusted accordingly. 

Milestone Extension: Magnuson-Stevens Fishery Conservation and Management Act, Section 305 Essential Fish Habitat (EFH) Consulta

On 1/13/23, BOEM notified NMFS that there would be an additional six-week delay in submitting an EFH Assessment that addressed comments submitted by NOAA Fisheries in October, 2022.  The delay is due to the fact that the developer would not be able to provide the information to BOEM for two more weeks and an additional 30 days is needed for BOEM's contractor to revise the EFH Assessment.  NOAA Fisheries' second EFH Milestone has been extended to allow

FAST-41 Missed Date:Environmental Impact Statement (EIS): Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action)

Triggered missed date from extending Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) within 30 days of its current target date which was 02/10/2023 and extended to 02/17/2023