USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Milestone Extension: Construction and Operations Plan

Submitted by cori.carraway@… on

BOEM needs to two weeks after ESA consultation concludes to incorporate the completed ESA consultation in the Final Environmental Impact Statement. Therefore,
BOEM is updating the FEIS milestone to March 1, 2024. ROD issuance and COP decision dates are dependent on the FEIS milestone, and so these milestone dates are also shifting by 98-days to April 1, 2024, and July 1, 2024, respectively.

Action
Project Name: Responsible Agency:
Bureau of Ocean Energy Management
Status:
In Progress
POC Name:
Christine Crumpton
POC Title:
Environmental Protection Specialist

Milestones:

Initial application submitted (Applicant Action)
Completed Date:
Application deemed complete (Agency Action)
Completed Date:
Final decision/agency action (Agency Action)
Current Target Date:
Milestone
Final decision/agency action (Agency Action)
Current Target Date:
Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/22/2024

9 out of 9

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Environmental Protection Agency

Environmental Protection Agency

Description:

Update: In October 2021, the project name changed from Vineyard Wind South to New England Wind to reflect restructuring of the project’s parent companies (for more information, see Vineyard Wind’s September 21, 2021 press release).

New England Wind is the proposal to develop offshore renewable wind energy facilities in BOEM Lease Area OCS-A 0534 along with associated offshore and onshore cabling, onshore substations, and onshore operations and maintenance (O&M) facilities. Park City Wind LLC, a wholly owned subsidiary of Avangrid Renewables, LLC, is the Proponent and would be responsible for the construction, operation, and decommissioning of New England Wind. New England Wind will be developed in two Phases. If approved, Phase 1, also known as the Park City Wind project, will be developed in the northeastern portion of Lease Area OCS-A 0534.  Phase 2, also known as Commonwealth Wind, will be located southwest of Phase 1.

FAST-41 provides increased transparency and predictability by requiring Federal agencies to publish comprehensive permitting timetables for all "covered" projects, and provides clear procedures for modifying permitting timetables to address the unpredictability inherent in the environmental review and permitting process for significant infrastructure projects. For more information, see "The FAST-41 Process" at  https://www.permits.performance.gov/fpisc-content/fast-41-process

The Executive Director granted a Bureau of Ocean Energy Management (BOEM) request to extend the NEPA, COP, Section 106, Sections 10/404, and OCS air permit actions completion date on May 10, 2023. The Executive Director determination is posted here.

The Executive Director granted a Bureau of Ocean Energy Management (BOEM) request to extend the Section 106 actions completion date on Nov 22, 2023. The Executive Director determination is posted here.

 

field_status
System Comments
Furthest out
Original Target Date: 10/01/2023
Milestone: Final decision/agency action (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

Final decision/agency action (Agency Action) extended by 274
From: 03/25/2024
To: 07/01/2024
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Final decision/agency action (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
Final decision/agency action (Agency Action)
Current Target Date: