Milestone Extension: Section 106 Review
The project sponsor presented new project information last fall on October 13, 2022, to BOEM, NOAA,
and USACE. The change in design for feasible wind turbine generator (WTG) locations involved removing 21 WTGs for the project. This change required additional analysis by BOEM for a new constructible preferred alternative that needed to be added to FEIS. The project design changed the impacts analysis for consultations. This action is dependent upon the ROD.