Milestone Extension: Section 106 Review

Submitted by craig.litteken… on

NTIA is requesting to modify the permitting timetable to allow the Project Sponsor to conduct additional surveys to support the Section 106 consultation, and more refined details regarding the proposed route alignment. Additional time is needed to conduct the surveys, some of which were not known at the time the original permitting timetable was established.  Additional time is also needed to conduct further coordination between the Project Sponsor and Tribes regarding alignment of the proposed route and protection of important resources.

Action
Project Name: Responsible Agency:
National Telecommunications and Information Administration
Status:
In Progress
SHPO:

New Mexico

THPO:
Navajo Nation
Pueblo of Acoma
Pueblo of Isleta
Pueblo of Zuni (Zuni Tribe of the Zuni Indian Reservation)

Milestones:

Consultation initiated with SHPO/THPO (Agency Action)
Completed Date:
Section 106 consultation concluded (Agency Action)
Current Target Date:
Milestone
Section 106 consultation concluded (Agency Action)
Current Target Date:
Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
10/29/2027

6 out of 9

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Broadband

SECTOR
Broadband

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of Commerce

LEAD AGENCY
Department of Commerce, National Telecommunications and Information Administration

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of the Interior

Department of the Interior, Bureau of Land Management

Department of the Interior

Department of the Interior, National Park Service

Department of the Interior

Department of the Interior, Bureau of Indian Affairs

Department of the Army

Department of the Army, US Army Corps of Engineers - Section 408

Description:

The Pueblo Education Network builds middle mile broadband infrastructure for tribes, enabling digital economy participation and effectuating last-mile internet access to homes and anchor institutions and tribal businesses. The Pueblo Education Network also creates a private education network connecting tribal PreK-20 schools and libraries to each other and to national research and education networks, modernizing Indian Education in the global information age.  The overall footprint is approximately 324 miles. The project originates in Albuquerque, New Mexico and travels through Isleta Pueblo, Acoma Pueblo, and Zuni Pueblo lands with the fiber path ending at the at the Zuni Elementary School, Zuni Head Start Building, Zuni Governor’s Office, and Zuni High School.  The fiber path will primarily be immediately adjacent to already established roads and will travel through private lands, Bureau of Land Management, US Forest Service, New Mexico State Land Office, Navajo Nation lands at Ramah, and Zuni Pueblo lands.

field_status
System Comments
Furthest out
Original Target Date: 01/31/2024
Milestone: Section 106 consultation concluded (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

Section 106 consultation concluded (Agency Action) extended by 91
From: 01/31/2024
To: 05/01/2024
Approver Comments
Executive Director Determination signed on 12/28/23 to approve the extension.
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Section 106 consultation concluded (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
Section 106 consultation concluded (Agency Action)
Current Target Date: