Milestone Extension: Magnuson-Stevens Fishery Conservation and Management Act, Section 305 Essential Fish Habitat (EFH) Consulta
The project sponsor requested the EFH milestones be revised to allow for additional time to conduct the EFH Assessment.
The project sponsor requested the EFH milestones be revised to allow for additional time to conduct the EFH Assessment.
BIA coordinated with the project sponsor (Santa Fe Indian School) and the lead agency (NTIA) to adjust the milestone deadlines. We propose bumping Zuni Agency ROW (where construction is intended to begin first) out 6 months and bumping Ramah Agency and Southern Pueblos Agency ROWs out 9 months. This will provide sufficient time for SFIS to submit complete ROW applications and for legal review of recently submitted waivers for definite location. For further justification, please see the attached.
BIA coordinated with the project sponsor (Santa Fe Indian School) and the lead agency (NTIA) to adjust the milestone deadlines. We propose bumping Zuni Agency ROW (where construction is intended to begin first) out 6 months and bumping Ramah Agency and Southern Pueblos Agency ROWs out 9 months. This will provide sufficient time for SFIS to submit complete ROW applications and for legal review of recently submitted waivers for definite location. For further justification, please see the attached.
BIA coordinated with the project sponsor (Santa Fe Indian School) and the lead agency (NTIA) to adjust the milestone deadlines. We propose bumping Zuni Agency ROW (where construction is intended to begin first) out 6 months and bumping Ramah Agency and Southern Pueblos Agency ROWs out 9 months. This will provide sufficient time for SFIS to submit complete ROW applications and for legal review of recently submitted waivers for definite location. For further justification, please see the attached.
Agency Milestone Date of 08/22/2025 for FWS determines ESA Consultation Package is Complete - Informal (Agency Action) has passed by 1 business days
BOEM conducted a comprehensive status of the development of the EIS and found that publication of the Draft EIS on September 19, 2025, is no longer feasible. BOEM estimated that publication of the Draft EIS would be delayed by approximately 10 months (308 day shift) to July 24, 2026. Therefore, subsequently adjusted the remaining milestones for actions accordingly.
BOEM conducted a comprehensive status of the development of the EIS and found that publication of the Draft EIS on September 19, 2025, is no longer feasible. BOEM estimated that publication of the Draft EIS would be delayed by approximately 10 months (308 day shift) to July 24, 2026. Therefore, subsequently adjusted the remaining milestones for actions accordingly.
BOEM conducted a comprehensive status of the development of the EIS and found that publication of the Draft EIS on September 19, 2025, is no longer feasible. BOEM estimated that publication of the Draft EIS would be delayed by approximately 10 months (308 day shift) to July 24, 2026. Therefore, subsequently adjusted the remaining milestones for actions accordingly.
BOEM conducted a comprehensive status of the development of the EIS and found that publication of the Draft EIS on September 19, 2025, is no longer feasible. BOEM estimated that publication of the Draft EIS would be delayed by approximately 10 months (308 day shift) to July 24, 2026. Therefore, subsequently adjusted the remaining milestones for actions accordingly.
BOEM conducted a comprehensive status of the development of the EIS and found that publication of the Draft EIS on September 19, 2025, is no longer feasible. BOEM estimated that publication of the Draft EIS would be delayed by approximately 10 months (308 day shift) to July 24, 2026. Therefore, subsequently adjusted the remaining milestones for actions accordingly.