USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Approved

Milestone Extension: Right-of-Way Authorization (DOI-BIA)

BIA coordinated with the project sponsor (Santa Fe Indian School) and the lead agency (NTIA) to adjust the milestone deadlines. We propose bumping Zuni Agency ROW (where construction is intended to begin first) out 6 months and bumping Ramah Agency and Southern Pueblos Agency ROWs out 9 months. This will provide sufficient time for SFIS to submit complete ROW applications and for legal review of recently submitted waivers for definite location. For further justification, please see the attached.

Milestone Extension: Right-of-Way Authorization (DOI-BIA)

BIA coordinated with the project sponsor (Santa Fe Indian School) and the lead agency (NTIA) to adjust the milestone deadlines. We propose bumping Zuni Agency ROW (where construction is intended to begin first) out 6 months and bumping Ramah Agency and Southern Pueblos Agency ROWs out 9 months. This will provide sufficient time for SFIS to submit complete ROW applications and for legal review of recently submitted waivers for definite location. For further justification, please see the attached.

Milestone Extension: Right-of-Way Authorization (DOI-BIA)

BIA coordinated with the project sponsor (Santa Fe Indian School) and the lead agency (NTIA) to adjust the milestone deadlines. We propose bumping Zuni Agency ROW (where construction is intended to begin first) out 6 months and bumping Ramah Agency and Southern Pueblos Agency ROWs out 9 months. This will provide sufficient time for SFIS to submit complete ROW applications and for legal review of recently submitted waivers for definite location. For further justification, please see the attached.

Milestone Extension: Outer Continental Shelf (OCS) Air Permit

BOEM conducted a comprehensive status of the development of the EIS and found that publication of the Draft EIS on September 19, 2025, is no longer feasible. BOEM estimated that publication of the Draft EIS would be delayed by approximately 10 months (308 day shift) to July 24, 2026. Therefore, subsequently adjusted the remaining milestones for actions accordingly.

Milestone Extension: Endangered Species Act Consultation (DOI-FWS)

BOEM conducted a comprehensive status of the development of the EIS and found that publication of the Draft EIS on September 19, 2025, is no longer feasible. BOEM estimated that publication of the Draft EIS would be delayed by approximately 10 months (308 day shift) to July 24, 2026. Therefore, subsequently adjusted the remaining milestones for actions accordingly.

Milestone Extension: Section 106 Review

BOEM conducted a comprehensive status of the development of the EIS and found that publication of the Draft EIS on September 19, 2025, is no longer feasible. BOEM estimated that publication of the Draft EIS would be delayed by approximately 10 months (308 day shift) to July 24, 2026. Therefore, subsequently adjusted the remaining milestones for actions accordingly.

Milestone Extension: Environmental Impact Statement (EIS)

BOEM conducted a comprehensive status of the development of the EIS and found that publication of the Draft EIS on September 19, 2025, is no longer feasible. BOEM estimated that publication of the Draft EIS would be delayed by approximately 10 months (308 day shift) to July 24, 2026. Therefore, subsequently adjusted the remaining milestones for actions accordingly.