USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Approved

Milestone Extension: Section 106 Review

A confluence of interconnected issues has contributed to the need to revise the overall permitting timetable for this project. The dates are shifting mainly because additional ESA species surveys have been added to the biological work plan in consultation with USFWS and the cultural resource surveys need to be re-performed.

Milestone Extension: Use Authorization (DOI-BOR)

A confluence of interconnected issues has contributed to the need to revise the overall permitting timetable for this project. The dates are shifting mainly because additional ESA species surveys have been added to the biological work plan in consultation with USFWS and the cultural resource surveys need to be re-performed.

Milestone Extension: Right-of-Way Authorization (DOI-BLM)

A confluence of interconnected issues has contributed to the need to revise the overall permitting timetable for this project. The dates are shifting mainly because additional ESA species surveys have been added to the biological work plan in consultation with USFWS and the cultural resource surveys need to be re-performed.

Coordination with all cooperating agencies and project sponsor has occurred for milestone schedule adjustments. 

Milestone Extension: Environmental Assessment (EA)

A confluence of interconnected issues has contributed to the need to revise the overall permitting timetable for this project. The dates are shifting mainly because additional ESA species surveys have been added to the biological work plan in consultation with USFWS and the cultural resource surveys need to be re-performed.

Coordination with all cooperating agencies and project sponsor has occurred for milestone schedule adjustments. 

Milestone Extension: Endangered Species Act Consultation (DOI-FWS)

The ESA milestones "FWS Determines ESA Consultation Package is Complete - Formal" and "ESA Consultation Concludes" are dependent on BOEM’s EIS action milestones. A shift of BOEM’s EIS action milestones by 119 days results in a commensurate shift to these ESA action milestones.  Therefore, an extension is requested based upon the extension of BOEM’s EIS milestones. The