FAST-41 Missed Date:Section 106 Review: Consultation initiated with SHPO/THPO (Agency Action)
Agency Milestone Date of 04/07/2026 for Consultation initiated with SHPO/THPO (Agency Action) has passed by 1 business days
Agency Milestone Date of 04/07/2026 for Consultation initiated with SHPO/THPO (Agency Action) has passed by 1 business days
Agency Milestone Date of 05/13/2026 for FWS determines ESA Consultation Package is Complete - Informal (Agency Action) has passed by 1 business days
Agency Milestone Date of 04/29/2026 for NOAA determines ESA Consultation Package is Complete - Informal (Agency Action) has passed by 1 business days
NRC submitted an EDD request on March 31 to the Permitting Council. The Executive Director granted a Nuclear Regulatory Commission (NRC) request to extend the final completion dates for the Section 106 consultation and the Bureau of Land Management's EA and Mine Plan of Operations on April 14, 2026.
The explanation for the milestone date change was outlined in the Executive Director Determination request submitted to the Permitting Council on March 30, 2026.
The explanation for the milestone date change was outlined in the Executive Director Determination request submitted to the Permitting Council on March 30, 2026.
The explanation for the milestone date change was outlined in the Executive Director Determination request submitted to the Permitting Council on March 30, 2026.
Agency Milestone Date of 04/02/2026 for Issuance of decision for permit/approval (Agency Action has passed by 1 business days
Agency Milestone Date of 03/22/2026 for Section 106 consultation concluded (Agency Action) has passed by 1 business days
At the request of the Project Sponsor, NTIA is seeking to extend the Project’s permitting timetable for the proposed actions and their associated milestones to allow the Project Sponsor to submit complete applications for rights-of-way.