Milestone Extension: Outer Continental Shelf (OCS) Air Permit

Submitted by craig.litteken… on

The project sponsor submitted an updated Construction and Operations Plan (COP) to BOEM on September 29, 2025. On October 1, 2025 the government shut down through November 12, 2025, impacting BOEM’s ability to review the COP submission. In addition, multiple comments were not addressed by the project sponsor in their September 29, 2025 COP submission and the project sponsor indicated that the Underwater Acoustic Assessment, Historic Resources Visual Effects Assessment, and Seascape and Landscape Visual Impact Assessment and associated COP updates would be submitted later in time.

BOEM expects a third and fourth COP submission prior to BOEM’s issuance of an NOI. Therefore, BOEM is shifting the completion of the Agency Review of Updated Application for Consistency with NOI Checklist milestone from November 28, 2025 to February 2, 2026 and completion of the Applicant Submits Updated Application for Consistency with the NOI Checklist from December 5, 2025 to May 28, 2027, which affects the rest of the NEPA schedule and EPA milestones were revised accordingly.

Action
Project Name: Responsible Agency:
Environmental Protection Agency
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
Planned
POC Name:
Suilin Chan
POC Email:

Description:

 

The EPA promulgated the Outer Continental Shelf (OCS) air regulations (40 CFR part 55) pursuant to Section 328 of the Clean Air Act (CAA). OCS permits contain various requirements including preconstruction permit requirements under the New Source Review (NSR) permitting program and operating permit requirements under the Title V permitting program. OCS permits also include New Source Performance Standards (NSPS), National Emissions Standards for Hazardous Air Pollutants (NESHAPS) and/or state and local air pollution control requirements for sources locating within 25 nautical miles of a states' seaward boundary (the line 3 nautical miles distant from a state’s coastline (9 nautical miles for Texas and Florida)). OCS permit issuance is a federal action that triggers EPA obligations under other federal statutes (e.g., National Historic Preservation Act (NHPA), Endangered Species Act (ESA), Magnuson-Stevens Fishery Conservation and Management Act (MSA)). The Bureau of Ocean and Energy Management (BOEM) is the lead Federal agency for ensuring compliance with ESA, MSA and NHPA. EPA is a co-action agency for all ESA, MSA and NHPA compliance activities associated with wind development projects on the Atlantic OCS. OCS permits are issued by EPA regional offices or delegated state and local permitting authorities. To date, the EPA has delegated the OCS permitting program to three states (Delaware, Maryland and Virginia) and four permitting authorities in California (San Luis Obispo County Air Pollution Control District (APCD), Santa Barbara County APCD, South Coast Air Quality Management District and Ventura County APCD).

Once an OCS permit application is determined complete by the applicable permitting authority, the permitting authority develops and issues a draft OCS permit. This draft OCS permit is open for public comment, usually for a 30-day public comment period, and after comments are evaluated, a response to comments document is developed. Public notice documents can be found on the applicable permitting authority website.

Although EPA’s OCS air permitting projects are not subject to the National Environmental Policy Act (NEPA), the EPA actively participates in BOEM's processes under NEPA for each of the OCS projects off the Atlantic coast and considers BOEM’s environmental analyses, including the NEPA Record of Decision (ROD), in the development of the OCS air permit for each source. The ROD explains BOEM’s decision under NEPA, the alternatives BOEM considered and BOEM’s plans for mitigation and monitoring, if necessary. EPA’s final permit decision occurs after the issuance of the ROD, which fulfills EPA’s statutory obligations under ESA, MSA and NHPA. The final permit must be issued no later than one year from the date EPA determines that the OCS permit application is complete. OCS permit application submission and review milestones are discussed in more detail below.

 

Milestones:

OCS Air Permit application submitted (Applicant Action)
Current Target Date:
Milestone Details

 

The Permit application must demonstrate compliance with all applicable requirements before it is submitted to the air permitting authority.  Those requirements are stated in 40 CFR Part 55, which include, but are not limited to, New Source Review (NSR) permitting, title V permitting, New Source Performance Standards (NSPS), National Emissions Standards for Hazardous Air Pollutants (NESHAPs) and any applicable state and local requirements.

Ahead of this milestone, EPA and the project developer conduct pre-application meetings as necessary to identify data and information needs, applicable OCS permitting requirements (e.g., air pollution control requirements, air quality modeling requirements) and policy issues for the proposed project.  It is recommended that preapplication meetings start to occur 9 months ahead of this milestone’s target date.  The air quality modeling protocol required as part of the permit application submittal is recommended to be sent to the permitting authority 6 months prior to this milestone.

 

OCS Air Permit application complete (Applicant Action)
Current Target Date:
Milestone Details

 

In accordance with 40 CFR 124.3)c), EPA notifies the permit applicant whether the permit application is complete or incomplete within 30 days after receiving such application.  If incomplete, EPA will ask the permit applicant to submit any additional information necessary to make the permit application complete.

Once the permit application addresses all EPA requirements, EPA will send a letter in writing to the permit applicant confirming that the permit application is complete.  The milestone will be checked  (on the dashboard) when completeness is confirmed.

 

Issuance of final decision/permit approval (Agency Action)
Current Target Date:
Milestone Details

The target date for this milestone is one year after the date EPA determines that the OCS air permit application is complete.  This milestone also reflects timely receipt of BOEM’s Record of Decision (ROD) for the project, which must occur prior to issuance of a final permit.  EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance.

Milestone
Issuance of final decision/permit approval (Agency Action)
Current Target Date:
Milestone Details

The target date for this milestone is one year after the date EPA determines that the OCS air permit application is complete.  This milestone also reflects timely receipt of BOEM’s Record of Decision (ROD) for the project, which must occur prior to issuance of a final permit.  EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance.

Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING

0 out of 0

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Description:

Attentive Energy LLC proposes to develop an offshore renewable wind energy facility to generate 1,545 megawatts of energy in the western portion of Bureau of Ocean Energy Management’s Lease Area Outer Continental Shelf (OCS)-A 0538.  OCS-A 0538 is located approximately 68 kilometers (36 nautical miles) offshore from the nearest shoreline point in New Jersey and 87 kilometers (47 nautical miles) from the nearest shoreline point in New York.  The wind energy facility would include wind turbine generators, foundations, inter-array cables, and one offshore substation with capacity for an offshore transmission network or one offshore substation and a stand-alone offshore transmission network platform with an independent foundation, offshore export cable, onshore export cables, and an onshore converter station to connect to the Larrabee Collector Station, a substation in Howell Township, New Jersey. 

field_status
System Comments
Furthest out
Original Target Date: 04/17/2028
Milestone: Issuance of final decision/permit approval (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

Issuance of final decision/permit approval (Agency Action) extended by 575
From: 04/17/2028
To: 11/13/2029
Approver Comments
Executive Director Determination signed on 1/29/2026 approving movement of the milestones.
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Issuance of final decision/permit approval (Agency Action)
Current Target Date:
Milestone Details

The target date for this milestone is one year after the date EPA determines that the OCS air permit application is complete.  This milestone also reflects timely receipt of BOEM’s Record of Decision (ROD) for the project, which must occur prior to issuance of a final permit.  EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance.

Furthest Original Target Date Milestone
Issuance of final decision/permit approval (Agency Action)
Current Target Date:
Milestone Details

The target date for this milestone is one year after the date EPA determines that the OCS air permit application is complete.  This milestone also reflects timely receipt of BOEM’s Record of Decision (ROD) for the project, which must occur prior to issuance of a final permit.  EPA generally estimates final permit issuance will occur 90 days after BOEM’s ROD issuance.