FAST-41 Missed Date: Right-of-Way Authorization (DOI-BLM)
Triggered missed date from extending Issuance of decision for permit/approval within 30 days of its current target date which was 03/31/2020 and extended to 06/29/2020
Triggered missed date from extending Issuance of decision for permit/approval within 30 days of its current target date which was 03/31/2020 and extended to 06/29/2020
Triggered missed date from extending Issuance of decision for permit/approval within 30 days of its current target date which was 07/02/2020 and extended to 07/13/2020
Triggered missed date from extending Issuance of Lead Agency Record of Decision within 30 days of its current target date which was 07/03/2020 and extended to 08/14/2020
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
09/29/2023
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Other Agencies with Actions or Authorizations:
Department of the Army, US Army Corps of Engineers - Regulatory
Department of the Interior, Fish and Wildlife Service
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/15/2026
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Other Agencies with Actions or Authorizations:
Department of the Interior, Fish and Wildlife Service
Department of the Army, US Army Corps of Engineers - Regulatory
Triggered missed date from extending Section 106 consultation concluded within 30 days of its current target date which was 02/21/2020 and extended to 06/15/2020
Final Required Milestone Date of 01/03/2020 for Section 106 consultation concluded has passed by 5 business days
Final Required Milestone Date of 03/31/2020 for Issuance of decision for permit/approval has passed by 5 business days
Final Required Milestone Date of 03/27/2020 for Issuance of Lead Agency Record of Decision has passed by 5 business days
PROJECT WEBSITE:
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/14/2021
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
LEAD AGENCY
Department of the Interior, Bureau of Indian Affairs
Other Agencies with Actions or Authorizations:
Department of the Interior, Fish and Wildlife Service