Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 08-04-2022 08-02-2022 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 09-04-2022 05-05-2023 07-19-2023 Yes
ESA Consultation Concludes (Agency Action) 06-04-2023 06-04-2023 12-01-2023 Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 08-04-2022 08-02-2022 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 09-04-2022 05-05-2023 07-19-2023 Yes
ESA Consultation Concludes (Agency Action) 06-04-2023 06-04-2023 12-01-2023 No
Planned
The lead action agency, BOEM, requested to change these milestone dates, because BOEM anticipates submitting a revised BA and response to agency comments on April 17, 2023.  This submission date may not provide the USFWS sufficient time to review and deem the consultation package is complete by the previous ESA consultation conclusion date which was May 5, 2023.  BOEM and USFWS had a call on March 28, 2023 to discuss and both agencies agreed to this new schedule.   , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 08-04-2022 08-02-2022 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 09-04-2022 05-05-2023 07-19-2023 No
ESA Consultation Concludes (Agency Action) 06-04-2023 06-04-2023 12-01-2023 No
Planned
FWS and BOEM are updating the second Milestone to allow additional time for coordination with BOEM and the applicant, as well as additional information, including surveys if needed, to complete the initiation package. In coordination with BOEM and the applicant, we anticipate revising the final Milestone to conclude consultation to September 18, 2023, to allow for formal consultation, if needed. The final Milestone date will need OED review and will be revised separately. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 08-04-2022 08-02-2022 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 09-04-2022 05-05-2023 --- No
ESA Consultation Concludes (Agency Action) 06-04-2023 06-04-2023 --- No
Planned
USFWS has requested additional review time of the current BA. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 08-04-2022 08-02-2022 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 09-04-2022 02-13-2023 --- No
ESA Consultation Concludes (Agency Action) 06-04-2023 06-04-2023 --- No
Planned
BOEM and FWS are revising the second Milestone to allow more time for them to review and revise the draft BA to complete the consultation initiation package. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 08-04-2022 08-02-2022 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 09-04-2022 01-13-2023 --- No
ESA Consultation Concludes (Agency Action) 06-04-2023 06-04-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 08-04-2022 08-02-2022 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 09-04-2022 11-04-2022 --- No
ESA Consultation Concludes (Agency Action) 06-04-2023 06-04-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) --- 08-11-2022 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) --- 11-04-2022 --- No
ESA Consultation Concludes (Agency Action) --- 06-04-2023 --- No