In Progress
FAST-41 Missed Date: Right-of-Way Authorization (DOI-FWS)
Final Required Milestone Date of 08/28/2020 for Issuance of decision for permit/approval has passed by 5 business days
FAST-41 Missed Date: Section 106 Review
Triggered missed date from extending Section 106 consultation concluded within 30 days of its current target date which was 01/24/2020 and extended to 10/20/2021
FAST-41 Missed Date: Environmental Impact Statement (EIS)
Triggered missed date from extending Issuance of Lead Agency Record of Decision within 30 days of its current target date which was 01/24/2020 and extended to 10/20/2021
FAST-41 Missed Date: Right-of-Way Authorization (DOI-FWS)
Triggered missed date from extending Issuance of decision for permit/approval within 30 days of its current target date which was 08/07/2020 and extended to 08/28/2020
FAST-41 Missed Date: Authorization and Certification
Final Required Milestone Date of 08/07/2020 for Issuance of decision for permit/approval has passed by 5 business days
FAST-41 Missed Date: Right-of-Way Authorization (DOI-FWS)
Final Required Milestone Date of 08/07/2020 for Issuance of decision for permit/approval has passed by 5 business days